2021 Lakeshore Drive
Sanitary Sewer Improvements

Top
 

Updates

Updates

Construction Update – 10/27

This Week (Week of October 25)

  • Construction crews will continue utility excavation pits moving from west to east along the corridor
  • Traffic access will remain restricted to one lane for local traffic only
  • Sanitary sewer work will continue with casing pipe installation moving from west to east
  • Sanitary sewer installation will continue from west to east.

Week of November 1

  • Utility excavation pit excavation work will continue from west to east along the corridor
  • Sanitary sewer casing and sewer construction will continue
  • Expect to see continued work on the West end of the project as services, existing mains, and manholes are connected.

Additional Information and Feedback

  • An access lane will be provided through the site at all times. Please be on the lookout for barrels and other traffic control items as you access the site. Through traffic should utilize the posted detour.
  • Mail and garbage service has been maintained throughout construction. The contractor will contact you and coordinate any adjustments that may be necessary if services need to be impacted.

For future project updates, go to the project website (IGLSD-ProtectingOurBlueWater.com) and sign up for email updates.

 


Construction Update – 10/12

Next Week (Week of October 18)

  • Construction crews will continue utility excavation pits moving from west to east along the corridor
  • Traffic access will remain restricted to one lane for local traffic only
  • Sanitary sewer boring construction will begin

Week of October 25

  • Utility excavation pit excavation work will continue from west to east along the corridor
  • Sanitary sewer boring construction will continue

Additional Information and Feedback

  • An access lane will be provided through the site at all times. Please be on the lookout for barrels and other traffic control items as you access the site. Through traffic should utilize the posted detour.
  • Mail and garbage service has been maintained throughout construction. The contractor will contact you and coordinate any adjustments that may be necessary if services need to be impacted.

For future project updates, go to the project website (IGLSD-ProtectingOurBlueWater.com) and sign up for email updates.


Construction Update – 9/17/2021

Next Week (Week of September 20)

  • Advanced notice detour signage will be installed.

Week of September 27

  • The project detour will go into effect on Monday, September 27.
  • Construction equipment will begin to be mobilized to the site.
  • Erosion control and temporary fencing work will begin
  • Excavation for utility location verification will begin
  • Boring pit excavation is expected to begin on the west end of the project (near Colcord Point) late this week.

Additional Information and Feedback

  • An access lane will be provided through the site at all times. Please be on the lookout for barrels and other traffic control items as you access the site. Through traffic should utilize the posted detour.
  • In general, mail and garbage service are anticipated not to be impacted during construction.  If drop-off/pick-up locations need to be adjusted during construction project staff will coordinate with you.
  • For future project updates, go to the project website (IGLSD-ProtectingOurBlueWater.com) and sign up for email updates.