ERWB Water Treatment Plant
Project Overview
The East Range Water Board, in partnership with the City of Aurora and Town of White are replacing the failing water treatment plant with an improved and sustainable water source and treatment facility. The project will construct a new water treatment plant, a new surface water intake structure, and 10,000 feet of water transmission line to extend water service to the Scenic Acres neighborhood. This project will regionalize the water system and provide sustainable water for the east range residents for the next 50 years.
Total Project Cost – $33 Million
Project Timeline
Spring 2024 – Begin Construction of Project
Fall 2024 – Completion of watermain extension to Scenic Acres
2026 – Final Completion of new Water Treatment Facility and Intake Structure
Project Updates
Check back here for project updates!
Documents
Contact Us!
For more information or questions regarding this project please contact:
- Josh Stier, Principal Engineer, at joshua.stier@bolton-menk.com
- Lucas Heikkila, City Administrator, at cityclerk@ci.aurora.mn.us