Project Updates

Week of August 6, 2018

  • Grading and roadway crews continue to work on Waconia Parkway from Pond Lane to CSAH 32.
  • Crews are also working on the pedestrian underpass and bridge on Waconia Parkway.
  • Utility crews are currently working on storm sewer installation between Community Drive and Waconia Parkway.
  • Grading crews are working on surcharge embankment removal in preparation of roadway construction from Community Drive to Waconia Parkway.

Please review the Traffic Impacts/Detours Page for upcoming road closure information!


Week of June 14, 2018

  • Grading and roadway crews are working on Waconia Parkway from Pond Lane to CSAH 32.
  • Draintile relocations are in progress along the closed portion of Waconia Parkway.
  • Utility crews are preparing to install the pedestrian underpass at the proposed CSAH 10 and Waconia Parkway intersection.

Please review the Traffic Impacts/Detours Page for upcoming road closure information!


Week of May 14, 2018

  • Grading crews are working on the trail between Community Drive and Highway 5.
  • Grading Crews are also working on installing surcharge material between Community Drive and Waconia Parkway.
  • Private utility crews are working on utility relocations along Waconia Parkway between Pond Lane and Sterling Road.

Please review the Traffic Impacts/Detours Page for upcoming road closure information!


November 3, 2017

Week of November 6

  • Signs will be installed
  • After this week, work will be suspended over winter and resume next spring.

October 12, 2017

Week of October 9

  • Site grading continued

Week of October 16

  • Site grading will continue

Week of October 2

  • Site grading continued
  • The Community Drive roundabout concrete sealing finished

Week of October 9

  • Trail base construction resume

Week of September 25

  • Site grading

Week of October 2

  • Site grading will continue
  • Trail base construction will continue

Week of September 18

  • Class 5 surfacing was installed on Orchard south of Highway 5 and that segment of road is now open to traffic.
  • Crews conducted final grading behind the curb lines starting near Highway 5 and moving north.
  • Trail base construction began

Week of September 25

  • Concrete crews will be installing the maintenance strip inside the medians and working on permanent sign base installation.
  • Trail base construction will continue

September 15, 2017

Week of September 11

  • Phase 1 is now open to traffic!
  • Roadway crews placed the aggregate base on Orchard south of Highway 5.
  • Crews installed signs between Highway 5 and Community Drive
  • Paving has been completed
  • Temporary striping was painted
  • Material placement on the north surcharge area will be complete this week.

Week of September 18

  • Crews will begin final grading behind the curb lines starting near Highway 5 and moving north.
  • Concrete crews will be installing the maintenance strip inside the medians and working on permanent sign base installation.
  • Trail base construction may begin at the end of the week.

September 8, 2017

Week of September 5

  • Concrete work completed this week
  • Aggregate base tolerance work will begin tomorrow and be complete by Saturday
  • Bituminous paving is scheduled to start on Saturday and be complete on Wednesday

Week of September 11

  • Paving crews will complete roadway paving by Wednesday.
  • Striping crews will be on site on Wednesday or Thursday
  • Sign installation crews will be on site on Wednesday or Thursday

September 1, 2017

Week of August 28

  • Concrete crews are working on mainline curb, which will be complete by the end of the week.
  • Concrete crews will be in on Friday to complete remaining curb, median noses and truck apron.
  • Grading crews are working on trial and backslope grading.
  • Sand is being hauled in and placed on both surcharge areas.

Week of September 5

No work will take place on Monday, September 4.

  • Concrete crews will complete catchbasin and other miscellaneous concrete work.
  • Road crews will work on tolerance the aggregate roadway base.
  • Sand and clay borrow will continue to be placed on the surcharge areas
  • Grading and topsoil placement will continue from Highway 5 to Community Drive.

Week of August 21

  • Completing sand installation at the Community Dr roundabout
  • Aggregate base installation will continue from Highway 5 and moving north to Community Dr.
  • Hauling and placement of stage 2 surcharge material will began late this week
  • Touching up grading on Highway 5 at the end of the week.
  • Permanent seeding on Highway 5 on Friday

Week of August 28

  • Curb and gutter crew is scheduled to begin work on Monday and continue through the week
  • Stage 2 surcharge operation will continue

Traffic Notes:

Trucks will again be hauling aggregate material to the site using County Road 10 / Waconia Parkway to access the construction entrance at the north end of the project. Please use caution and be aware of turning trucks on County Road 10 / Waconia Parkway between Pond Lane and County Road 32.


Highway 5 at Orchard Road is now open.

Week of August 7

  • Road crews began installing material between 94th Street and Community Drive.
  • Grading crews began working on subgrade preparation near Community Drive and grading shoulders and back slopes north of Highway 5.
  • Sand has been installed up to the Community Drive roundabout

Week of August 14

  • Concrete crews will install curb and gutter from Highway 5 to 94th Street
  • Concrete crews will install median and pedestrian ramps from Highway 5 to 94th
  • Road crews will continue to install aggregate base from 94th Street to Community Drive.
  • Paving crews will begin paving late in the week

August 4, 2017

Highway 5 is closed at Orchard Rd. Please see the map below for detour information:

Week of July 31

  • Roadway crews are installing aggregate base. Paving will continue through Saturday
  • Crews installing concrete curb and gutter and medians at the TH 5 intersection
  • Roadway crews began installing sand sub-base on CSAH 10 north of TH 5

Week of August 7

  • Concrete joint sealing will begin on Monday
  • Striping crews are scheduled to complete work on TH 5 Wednesday
  • Sign installation will be completed on Monday and Tuesday
  • Crews will continue with subgrade and sand up to Community Drive
  • Bike trail work will begin south of TH 5
  • Boulevard and median topsoil and seeding will be completed early in the week

 


July 21, 2017

Highway 5 is closed at Orchard Rd. Please see the map below for detour information:

Week of July 24

  • Roadway aggregate base placement occurred
  • Curb was installed within the Highway 5 roundabout
  • Mainline curb is scheduled to be complete by Saturday, and concrete crews will move into median and truck apron paving

Week of July 31

  • Utility crews will have all utilities installed up to Community Drive by the end of the week
  • Roadway crews will install the final lift of aggregate base
  • Concrete crews will complete driveway and pedestrian ramp construction early in the week.
  • Paving crews are scheduled to begin paving at the end of the week.
  • Roadway lights and signs will be installed