2025 Pavement Management Project

Overview

Project Overview

The general contractor for the 2025 Pavement Management Project is McNamara Contracting. Construction is anticipated to begin in the Spring of 2025 with completion in Fall of 2025. This project includes the rehabilitation of the Hidden Valley neighborhood.

Street construction is weather dependent, therefore the schedule is subject to change. There will be ongoing communication providing project schedule updates.

Safety is the highest priority of everyone involved in this project. While the contractor will do their best to provide warning signs, barricades, and observation within the project areas, we do ask that you remind children to stay clear of the construction site and equipment.

Project Updates

Ongoing work (subject to change, weather dependent)

Phase 1:

Work completed in the week of July 28:

  • Seed & Hydro mulch behind curb
  • Corrective concrete replacement

Anticipated work for the week of August 4:

  • Finish raising manhole and valves – pending private utility locates

Phase 2:

Work completed in the week of July 28:

  • Started raising manhole and valves

Anticipated work for the week of August 4:

  • Finish raising manhole and valves – pending private utility locates

Phase 3:

Work completed in the week of July 28:

  • Curb removals & replacement
  • Spot utility repairs
  • Street light service cabinet swap

Anticipated work for the week of August 4:

  • Pavement milling – 8/5
  • Aggregate base mixing & shaping.

*All work dates are weather dependent*

Thank you for your patience during this project. If you have any questions or concerns reach out to the project hotline at 952-836-7114 or email cg2025@bolton-menk.com

Type of Construction

The project involves the removal and replacement of the asphalt pavement, spot curb replacement, and trail resurfacing. Minor utility repairs will be performed as needed on watermain, sanitary sewer, storm sewer, and streetlights. Improvements will be made to Hidden Valley Park by adding a patio and small sports court.

Location Map

Contact Us!

Have any questions about construction? Email us and a member of the project team will get back to you as soon as possible. See contact info below.

Hotline Email Address:

Project Representative

Brice Mantel

Click below to sign up for project updates!

To sign up for project updates, please enter your email below.