City of Waconia, East Frontage Road Improvement Project
Top
 

Project Updates

Project Updates

May 13, 2022

Utility work has been completed. Beginning next week, the street will be brought up to grade for the new elevations. This portion of construction will also install draintile, sand, and aggregate to build up the roadway section. It is anticipated that the street and parking lot work will take approximately 3-4 weeks. The East Frontage Road Parking Lot will have turf restoration by next week.

May 6, 2022

Storm sewer construction continues this week and is anticipated to be completed early next week. One last water service is anticipated for Monday, May 9. Following the storm sewer, the street will begin to be brought up to grade for the new elevations. This portion of construction will also install draintile, sand and aggregate to build up the roadway section. The East Frontage Road Parking Lot, that was constructed last fall, is anticipated to have the sidewalk poured on Friday, May 6, with turf restoration to follow on next week.