May 3, 2021

Work Completed

  • Sanitary sewer main was installed on Main St from 190th St (Hwy 109) to Elm St.
  • Water main is in from Date St to 190th St (Hwy 109).
  • Most of the storm sewer mainline was installed on Main St from 190th St (Hwy 109) to Elm St.
  • About half of services have been installed.

Work Planned

  • Removals from Date St to the railroad tracks are potentially planned for Thursday.
  • Continue service and storm sewer work.

Past Updates

April 26, 2021

Work Completed

  • New water main was installed on Main St between Date St and 190th St (Hwy 109).
  • The majority of the water main work on 4th St is complete.
  • Sanitary sewer main was installed on Main St between Elm St and Linder St.
  • Some services have been hooked up.

Work Planned

  • Complete the sanitary sewer work
  • Continue service and storm sewer work.

April 19, 2021

Work Completed

  • New water main was installed on Main St between Cedar St and 190th St (Hwy 109).
  • The majority of the water main work on 4th St is complete.
  • Services have not been hooked up yet.
  • Sanitary sewer work has begun on Main St between Cedar St and Elm St.

Work Planned

  • Sanitary sewer and water service work will continue.