2019 STREET IMPROVEMENTS
Construction Update: September 27, 2019
Click here to view the phasing map.
Week of September 23
- Work on 170th Street was continued. The entire street was paved, and the shoulders were completed.
Week of September 30
- 170th Street will have pavement striping completed. After this, the entire project will be substantially completed.
- At this point, the only other work remaining will be to address miscellaneous punchlist items or small items needing correction.
Parking, access, and detour information
All project streets are open for Empire residents to utilize, but it is still a construction zone, so please slow down, especially while workers are present. Residents will have access to their driveways for the remainder of the project, but keep in mind that short access delays may still occur. During the day, streets with work occurring may inhibit through access where the contractor is currently working. Residents will still have access to their driveways from one way or the other on the street – you may just have to go around the block.
We apologize for the inconveniences of the project and appreciate your patience while we work to improve your roads!
Contacts
If you have any questions or concerns regarding this update or the project in general, please contact Brad Fisher at 612-759-7240.