Project Overview
The project will address the need for utility and pavement updates/upgrades on North Shore Trail from 235th St to Highway 97 as well as the Itasca Ave neighborhood and the Hayward neighborhood south of North Shore Trail. Estimated construction cost is $5.5 million dollars with construction scheduled to being in mid-May and be completed by the end of October. Xcel gas will also be installing new gas mains and services from 235th to and including Jason Ave on North Shore Trail, and on Hayward Ave.
The anticipated start date is Monday, June 9, 2025.
Project Objectives
To remove and replace the failing storm sewer culverts, repair sanitary sewer facilities, and to create a safer and smoother road for residents while maintaining the existing rural features within the projects limits.
Project Map
Schedule
The following is an overview of the contractor’s schedule.
Phase 7: May 27 – June 16
Phase 6: June 9 – June 25
Phase 5: June 25 – July 14
Phase 4: July 10 – July 30
Phase 3: July 30 – August 12
Phase 2: August 12 – September 9
Phase 1: September 9 – October 10
To view a more detailed schedule, visit the Master Schedule.
Contractor
Bituminous Roadways