Updates

Construction Updates

August 22, 2024

Starting tomorrow, Friday (8/23), the contractor plans to prepare the road for paving. The first step will be to remove the excess existing gravel to make room for the new pavement. During this process, access to driveways will be available but temporarily interrupted. Please have all parked vehicles off the road by 8am tomorrow morning. Thank you for your patience throughout the past few weeks!

Contact Us

If you have questions, please contact Rob Coughlin 507-508-5712 or Drew Weber at 507-469-0306.

 

August 19, 2024

The contractor began excavating and placing new gravel based at the Highway 56 access just north of Casey’s.  On Tuesday and Wednesday, they plan to continue east along 4th St NW.  Driveway access may be limited during this grading process between 8am and 5pm.

 

August 16, 2024

The contractor plans to perform a sewer repair on 3rd St NW on Tuesday (8/20) and Wednesday (8/21).  Driveway access will be obstructed between 9am and 5pm for all homes within the cul de sac east of House number 608.

 

August 8, 2024

Grinding of the existing pavement has been rescheduled for Monday 8/12.  Please have all vehicles off the road by 7am on Monday.  Vehicles can remain in driveways, but access to individual driveways will be periodically interrupted throughout the grinding process.

 

August 5, 2024

  • The contractor has completed all subdrain work throughout the project.
  • Approximately 50% of the concrete work has been completed.
  • Grinding of the existing pavement is tentatively scheduled for 8/14 (subject to change). Road building and paving to follow.

 

July 10, 2024

  • During the week of 7/7, the contractor plans install subdrain pipe along 4th St NW. Please limit parking along the street to a minimum.
  • The contractor will continue to maintain access to every driveway with limited interruptions during subdrain installation.
  • The contractor will also be installing sump pump services during this time. The current stakes with pink paint in homeowners’ yards are proposed locations. If you prefer a different location, please contact Chason Mierau.
  • As per city contract, sump services will be installed at the right of way line and the remaining connection is the homeowner’s responsibility.

 

June 25, 2024

As mentioned in the newsletter, the contractor is scheduled to begin work during the week of July 8th.  In preparation, they will be mobilizing equipment and materials as early as this week.  Saw cutting is also scheduled for Thursday June 27th. This will be done along 4th St NW, just a few feet off the curb, and run parallel for the entirety of the street. Please have all vehicles off 4th St NW on June 27th from 7:00am to 6:00pm.