Project Schedule

Week of 4/12/2021

  • Tree Removals will begin for the remainder of the project area (Phase 3),  starting on Phase 3A and working through all Phase 3 until they are complete.
  • Temporary Water will be set up for Phase 3A (Ashley from Goodrich to Excelsior and Boyce from Blake to Oakwood).
  • Punch list and cleanup work on streets completed in 2020 (Phases 1 and 2A).

Week of 4/19/2021

    • Pavement removals will occur in Phase 3A including reclaiming (grinding up) the asphalt road and removing driveways and walkways.
    • Utility work will begin in Phase 3A with sanitary sewer, storm sewer, and watermain.

Phasing Map

Click to view a larger version.

What to Expect During Construction

If you have questions or are curious on the construction process for your street, the link to the video below might be able to help! This video goes over the general process of a typical residential reconstruction project with the replacement of streets and utilities.

https://www.youtube.com/watch?v=iyFh4_3VpGY&feature=youtu.be

Sign Up for E-Notices

The Project Team has talked with many residents about opting out of paper notices as much as possible to rely on mostly e-notices. If you have not been contacted about this yet and would like to opt out of paper notices as much as possible, please email Madeline.Lunzer@bolton-menk.com with your name, street address, preferred email address, and phone # if you would also like to sign up for text message updates.

EMAIL & TEXT MESSAGE UPDATES

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

SIGN UP FOR E-NOTICES

The Project Team has talked with many residents about opting out of paper notices as much as possible to rely on mostly e-notices. If you have not been contacted about this yet and would like to opt out of paper notices as much as possible, please email Madeline.Lunzer@bolton-menk.com with your name, street address, preferred email address, and phone # if you would also like to sign up for text message updates.


Contacts

Project Help Line
612-619-7772


Nick Amatuccio, PE
Project Engineer
612-965-3926
nickam@bolton-menk.com


Josh Hrabe
Construction Observer
612-965-2473
joshhr@bolton-menk.com


City of Hopkins

Eric Klingbeil, PE
Assistant City Engineer
952-548-6357
eklingbeil@hopkinsmn.com


What to Expect During Construction

If you have questions or are curious on the construction process for your street, the link to the video below might be able to help! This video goes over the general process of a typical residential reconstruction project with the replacement of streets and utilities.

https://www.youtube.com/watch?v=iyFh4_3VpGY&feature=youtu.be