Construction Start Up

Starting Monday 8/17/20, the contractor is planning to start reclaim and removal work on the 200 blocks of Interlachen Road and Hawthorne Road. Utility work is scheduled to begin later in the week of 8/17.

We apologize for any inconvenience this may cause you. Thank you for your cooperation and understanding throughout the process of improving your street and utilities.

Please call the Project Help Line at 612-619-7772 if you have any questions or concerns.

Phase 1C Driveway Layout Requests

The project team asks that all residents in Phase 1C provide their driveway layout requests to Josh Hrabe, Inspector On-Site, by this Friday, August 14

Construction Start Up

Starting Monday 8/10/20, the contractor is planning to start utility work on the 200 blocks of Holly Road and Homedale Road.

Starting Monday 8/10/20, and for the foreseeable future, the project team asks that any residents living on the 200 blocks of Holly Road or Homedale Road needing to leave during typical working hours (7 AM to 7 PM) to please park on adjacent streets such as the 100 Blocks of Holly Road or Homedale Road. Precautions will be taken so that emergency vehicles will be able to access the 200 blocks of Holly Road and Homedale Road if need be.

Access to driveways will be made available after working hours Mondays-Fridays and on weekends unless Saturday work occurs.

We apologize for any inconvenience this may cause you.  Thank you for your cooperation and understanding throughout the process of improving your street and utilities.

Please call the Project Help Line at 612-619-7772 if you have any questions or concerns.

Construction Update: August 7, 2020

Weekend work is not anticipated to occur this Saturday.

Week of August 3

Phase 1A

  • Restoration work behind the curb continued.

Phase 1B

  • Concrete curb & gutter was installed.

Phase 1C

  • Utility work wrapped up on Meadowbrook.
  • Street grading began on the rest of Goodrich.

Phase 1D

  • Street grading wrapped up and concrete curb & gutter was installed.

Phase 1E

  • Construction began with temp water installation and pavement removals.

Week of August 10

Phase 1A

  • Restoration work behind the curb will continue including sod installation.

Phase 1B

  • Concrete driveways will be poured and crews will prepare the gravel base for the first layer of asphalt paving.

Phase 1C

  • Street grading will begin on Meadowbrook.

Phase 1D

  • The first layer of asphalt will be paved on Blake Road.
  • Restoration work will begin on Blake.
  • The concrete barriers will be pulled off of the road and two-way traffic will resume at the end of the week.

Phase 1E

  • Utility work will occur on Holly and Homedale.

Existing Watermain

The contractor is currently replacing the old cast iron watermain pipe with new ductile iron pipe on Goodrich St. Below are pictures of the existing watermain pipe that crews are pulling out of the ground. The existing pipe is old, extremely brittle, and breaking up as it’s pulled out of the ground. This pipe would not have lasted much longer so it is more efficient to replace it now while the street is being redone.

Access and Parking

When the street and utilities are under construction, the contractor will need all of the space in the street possible. Therefore, parking will not be allowed on the project area streets under construction during the working hours.  Access to driveways will be provided as much as possible. Temporary access restrictions should be anticipated during the work day.  The project team understands the need for access to each property, therefore the streets will be temporarily restored at the end of each work day and access to private driveways will generally be available each night.

Garbage and Recycling Service

Please make sure that you have your garbage and recycling bins out the night before your scheduled pick-up day. Garbage and recycling will be picked up throughout the neighborhood starting at 6 AM on your scheduled pick-up day. If the garbage or recycling truck cannot access your street due to construction, construction crews will label the bins and bring them to the nearest accessible intersection for pick up in the morning and then bring the bins back in the evening. Please continue to place the bins at the end of your driveway like normal, just the night prior to pick-up.

Phasing Map

Click to view a larger version.

EMAIL & TEXT MESSAGE UPDATES

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

SIGN UP FOR E-NOTICES

The Project Team has talked with many residents about opting out of paper notices as much as possible to rely on mostly e-notices. If you have not been contacted about this yet and would like to opt out of paper notices as much as possible, please email Madeline.Lunzer@bolton-menk.com with your name, street address, preferred email address, and phone # if you would also like to sign up for text message updates.


Contacts

Project Help Line
612-619-7772


Nick Amatuccio, PE
Project Engineer
612-965-3926
nickam@bolton-menk.com


Josh Hrabe
Construction Observer
612-965-2473
joshhr@bolton-menk.com


City of Hopkins

Eric Klingbeil, PE
Assistant City Engineer
952-548-6357
eklingbeil@hopkinsmn.com


What to Expect During Construction

If you have questions or are curious on the construction process for your street, the link to the video below might be able to help! This video goes over the general process of a typical residential reconstruction project with the replacement of streets and utilities.

https://www.youtube.com/watch?v=iyFh4_3VpGY&feature=youtu.be