Construction Update

Week of May 9th

  • Traffic control devices and lane closures occurred on 17th Avenue N.
  • Pavement removals took place on the west portion of phase 1.
  • Utility excavations for watermain installation and drilling operations occurred in phase 1.
  • Northbound 17th Avenue was reopened to all lanes of traffic.

Week of May 16th

  • Utility excavations for phase 1 (west portion) will continue.
  • Contractor will begin preparing for the utility work for phase 1 (east portion) along 5th Avenue North, Wayside Road, and Oak Ridge Road.

Week of May 23rd

  • Utility work to continue on phase 1 (west portion)
  • Utility work including drilling of new watermain will occur on phase 1 (east portion)
  • Intersection closure at Wayside Road and 5th Avenue North.