2022 Infrastructure Improvements Project

To sign up for email and text updates, please click the link below.

JORD_2022_Infrastructure_Imprvmnts_8X11P_Lukas Wheeler

Construction Updates

9/2:

Please view the September Construction newsletter.

Alleys: Construction began on the four alleys between Mertens street and  Rice street this week! A few notes regarding upcoming construction:

  • The contractor will do their best to restore access to the alleys at the end of each working day.
  • When the alley is inaccessible, residents should park on adjacent streets. Please note, recreational vehicles and trailers cannot be parked on the street for more than 24 hours per City ordinance. Please plan accordingly. 
  • Additional grading work in the alleys will occur during the week of 9/5
  • Concrete work is tentatively scheduled late in the week of 9/5. There will not be access to the alleys for 5-7 days after the concrete is poured to allow for the concrete to cure/harden. Please note this work is weather and schedule dependent and could change on short notice. Additional notification will be distributed to residents prior to the upcoming concrete work.
  • Garbage Pickup: garbage will be picked up at the front of your residence, as access to the alleys for garbage truck will be restricted. Please place your garbage can at the street in front of your property on your respective garbage day. Garbage cans must be pulled off the street after your garbage day. Cans cannot be stored on the street.

Whispering Meadows:

  • Watermain installation is complete with exception of some minor service work scheduled for early next week.
  • A majority of the concrete curb and gutter and driveways were installed this week. The remainder of the concrete work is tentatively scheduled for mid to late next week. New concrete cannot be driven over or parked on for 5-7 days after it is poured to allow for the concrete to cure/harden. Please note this work is weather and schedule dependent and could change on short notice. Additional notification will be distributed to businesses prior to the upcoming concrete work.
  • Additional roadway grading will be completed over the coming weeks with base course paving tentatively scheduled for mid to late September. Additional notification will be distributed prior to paving. 

Please note that all  work is weather dependent and the schedule could change on short notice. For more information on the project, please visit the project website at www.jordanmnengineering.com

 


Project Status, Schedule, Updates

October 4, 2021: Council Authorizes the preparation of Feasibility Report
January 10, 2022: Council Received Feasibility Report and Orders Public Improvement Hearing
February 1 2022: City holds Public Information Meeting #1
February 14, 2022: Council conducts Public Improvement Hearing and considers Ordering Final Plans
March 28, 2022: Final Plans are presented to Council, Council considers authorizing public bidding
April 25, 2022: Council Receives Bids and consider ordering Assessment Hearing
Early May 2022: City holds Public Information Meeting #2
May 23, 2022: Council conducts Assessment Hearing, considers Adopting Assessments, Consider Awarding Construction Contract
Construction:

El Dorado Drive & Seville Drive
Begin Construction:  Week of July 4th
Remove Pavement: July 11th
Utility Construction: July – August
Roadway Construction: August
Restoration /Cleanup: September

Alley Improvements
Alley Construction: Late July – August
Restoration /Cleanup: September


Project Summary:

The project includes the following improvements

  • Whispering Meadows (El Dorado Dr and Seville Dr)
    • Replacement of Watermain
    • Resurfacing of street pavement
    • Addition of concrete sidewalk along the north and west side of the roadway
    • Replacement of broken concrete curb/gutter panels
  • Alley Improvements
    • Improvement of 4 blocks of alley located ½ block north of TH 282 (Second St), between Mertens Street and Rice Street
    • Drainage Improvements
    • Paving the surface of existing gravel alleys

Project Documents:


Project Contacts:

Luke Wheeler, of Bolton & Menk is the Assistant City Engineer and will be primary contact representing the City and its residents and business owners.  If you have any questions regarding the project you may contact him at (612) 597-9105 or Luke.Wheeler@bolton-menk.com.

Mike Waltman, of Bolton & Menk is the Jordan City Engineer and Project Manager.  He can be reached at (952) 890-0509 or mikewa@bolton-menk.com


FAQ’S

Q: When will this project be constructed?

A: The construction contract will be awarded in the spring of 2022. Construction is expected to start late spring or early summer and last approximately 12 weeks. This will be updated with more detail once the contract is awarded and the contractor submits their proposed construction schedule.

Q: What work will be done?

A: 

Whispering Meadows:

The preliminary project scope includes replacement of watermain which has a history of breaks, resurfacing of the street pavement, addition of concrete sidewalk along the north and west side of the roadway, and  replacement of broken concrete curb/gutter panels.

Alley Improvements:

The alley Improvement project scope is planned to include grading the existing gravel base and paving the alley. The alley will be analyzed to determine whether the addition of storm sewer is needed to improve drainage, though some blocks of alley already have storm sewer in place

Q: When will the contractor be working?

City working hours are 7 AM to 7 PM M-F and 8 AM to 6 PM on Saturday as necessary

Q: Is there someone I can talk to about the construction?

A: Luke Wheeler, of Bolton & Menk is the Assistant City Engineer and will be primary contact representing the City and its residents and business owners.  If you have any questions regarding the project you may contact him at (612) 597-9105 or Luke.Wheeler@bolton-menk.com.

Mike Waltman, of Bolton & Menk is the Jordan City Engineer and Project Manager.  He can be reached at (952) 890-0509 or mikewa@bolton-menk.com