Project Updates – October 30, 2023
Work Completed Last Week:
- Minor grading around each of the ponds and added seed to areas that were disturbed.
- Tomorrow they plan on painting the centerline of the street from Vadnais Boulevard to Vadnais Boulevard.
Work Completed This Week:
- Began working on the fence along the backside of the trail to protect users from the steeper slopes.
Anticipated Work for Next Week:
- Finishing fence work installation.
- Wrapping minor punch list items.
This will be the final project update. The project team very much appreciates everyone’s patience throughout construction!