2022 Street Improvements
Project Updates
Contact
Carl Lind, Project Inspector
Cell: 651-302-1155
Email: [email protected]
Eric Seaburg, City Engineer
Cell: 763-732-8751
Email: [email protected]
Bill Dircks, Public Works Director
Cell: 651-775-7525
Email: [email protected]
Project Updates – 10/7/22
Woodlynn Avenue
Work Completed This Week:
- Striping
- Minor paving
Anticipated Work Next Week:
- No work anticipated
Documents
Yorkton Ridge
- Feasibility Report
- October 20, 2021 Neighborhood Meeting Presentation
- December 15, 2021 Public Improvement Hearing Presentation
Maple Lane – Jackson Street
- Feasibility Report
- October 20, 2021 Neighborhood Meeting Presentation
- December 15, 2021 Public Improvement Hearing Presentation
Woodlynn Avenue
Ryan Drive