2024 Forcemain Improvements

Top
 

Schedule

Schedule

Schedule

Nov. 11, 2024 – Construction Starts

Nov. – Dec. 2024 – Orleans forcemain pipe fusing

Dec. 2024 – Feb. 2025 –Winter Work as weather allows

Mar. – Apr. 2025 – Garlock forcemain pipe fusing

Mar. – May 2025 – Utility verifications and adjustments

Apr. – Sept. 2025 – Garlock and Green Acres forcemain drilling

Jun.- Sept. 2025 – Manhole and trenched pipe installation

Aug. – Sept. 2025 – Nodlands and Orleans forcemain

Sept. 22, 2025 – Construction substantially complete

Oct. 31, 2025 – Construction Ends

*The above schedule is tentative based on weather conditions and subject to adjustments.

Sign up for Project Updates!

Sign up for project updates

To sign up for project updates, please enter your contact information below.

Project Contacts

Josh Pope
District Engineer
Bolton & Menk, Inc.
Joshua.Pope@bolton-menk.com
(712) 363-8638

Katy Gehler
Project Manager
Bolton & Menk, Inc.
Katheryn.Gehler@bolton-menk.com

Austin Crew
Construction Project Representative
Bolton & Menk, Inc.
Austin.Crew@bolton-menk.com
(515) 567-0983