Project Summary

In 2020, the City of Orono will be making improvements to various roads throughout the city. These roads include Rest Point Lane, Togo Road, Livingston Avenue, Windjammer Lane, Briar Street, Fox Street, Lyman Avenue, and Smith Avenue. Weekly updates will be posted here once construction begins.

Weekly Update – October 15, 2020

This is the last project update for the 2020 Street Improvements.

  • All streets have been resurfaced and paved.
  • The contractor will be working on final restoration in the next few weeks before winter.
  • Any restoration that doesn’t get completed this year will be finished in the spring. We will perform final walkthroughs on all the streets in the spring to make sure all restoration is finished properly. If you have any questions about the restoration on your property please contact Luke Connor (507-995-0465).

Thank you everyone for being patient during construction this summer.

Open House Presentation

To learn more about this project, including construction details, impacts, and timelines, please watch the presentation below.

Note: make sure your volume is up, the presentation is narrated.

Contact Us!

Luke Connor (Primary Contact)
Project Representative
507-995-0465
lucas.connor@bolton-menk.com

Adam Edwards
Director of Public Works/City Engineer
952-249-4600
aedwards@ci.orono.mn.us

Jeffrey Weyandt
Bolton & Menk, Inc.
952-448-8838
jeffrey.weyandt@bolton-menk.com