No updates.
The remaining concrete curb and driveway aprons are complete. Five of the asphalt driveways have been repaved; the remaining driveways are planned to be repaved on Friday, Oct. 9. The final layer of pavement is also planned to be paved on Friday, Oct. 9. The final concrete driveway is planned to be poured on Saturday, Oct. 10.
No updates.
No updates.
No updates.
No updates.
No updates.
Reminder: All work is weather dependent and subject to change. If you have any questions or concerns regarding construction, do not hesitate to reach out to one of the project contacts. Thank you for your patience and understanding during the construction of these improvements!
Dylan Zellmann
Bolton & Menk Project Representative
651-421-4968
dylan.zellmann@bolton-menk.com
Adam Edwards
Director of Public Works/City Engineer
952-249-4600
aedwards@oronomn.gov