C.S.A.H. 34 & C.S.A.H. 35 Improvements
Brown County & the City of Sleepy Eye
St. Mary’s Street / 3rd Avenue NE and 1st Avenue Improvements
Project Overview
This summer, Brown County and the City of Sleepy Eye will be improving parts of two County Roads through Sleepy Eye: County State Aid Highway (C.S.A.H.) 34 and County State Aid Highway (C.S.A.H.) 35. This work will be split into two different sections. The general contractor will be M.R. Paving & Excavating.
C.S.A.H. 34 – St. Mary’s Street and 3rd Avenue NE State Aid Project No. 008-634-011
The work on C.S.A.H. 34 will begin on St. Mary’s Street at the intersection with Trunk Highway (T.H.) 4 and extend to intersection with 3rd Avenue NE. From there it will turn north and continue on 3rd Avenue NE and end at Windsor Road.
Work on this portion of the project will include the complete replacement of all pedestrian ramps that do not conform to the current ADA standards. Select curb & gutter spots in disrepair will be removed and replaced. Utilities will be replaced in the intersection of St. Mary’s Street and 1st Avenue along with minor utility work in select areas along St. Mary’s Street. The entire street surface along this route will be milled down and then overlayed with new bituminous pavement.
The streets on this portion of the project will be open to traffic for most of the duration of the work with the exception being during the spot utility work in and near the intersection of St. Mary’s Street and 1st Avenue and during the paving operations.
C.S.A.H. 35 – 1st Avenue State Aid Project No. 008-635-015
The work on C.S.A.H. 35 will begin at Walnut Street and end at St. Mary’s Street. The intersection of 1st Avenue and Trunk Highway (T.H.) 14 is not included with this work. Work will extend up to both sides of T.H. 14 but not through the intersection, meaning T.H. 14 will remain open for the duration of the project.
This portion of the project is a complete reconstruct. All the utilities (sanitary sewer, storm sewer, and watermains) will be reconstructed. Sanitary sewer and water services will be reconstructed from the mains to the Right of Way. The entire street surface and subbase, curb & gutter, sidewalks, and driveways will be replaced within the County’s Right of Way.
Along with the street and utility work, the railroad crossings will be improved. The northern spur of the railroad will be removed. The two other spurs will be replaced with all new concrete planking. The main rail (the southern track) will be left in place.
This work will cause 1st Avenue to be closed for much the duration of this project. However, a minimum of one east-west crossing on 1st Avenue north of the railroad tracks will be open to traffic at all times.
Weekly Updates
Weekly Update – 11/18/21
1st Avenue is open! Work on the street is complete for the year. Next year, crews will come back to put the final layer of pavement on. This top layer is left until the following construction season to give the ground a freeze-thaw cycle to settle out. The final layer will then fill in any spots that settled out. Striping will be left off until next year once the final layer of pavement is complete.
The railroad crossing is planned to be completed within the next year to year and a half. Originally, the crossing was planned to be completed this year but due to schedule changes by the railroad, the work will now have to be completed in an 18-month time frame. The two north spurs will be replaced with all new concrete planking and the pavement between the rails will also be replaced. Sidewalk will be extended across the tracks on both sides.
Weekly Update – 10/21/21 Road Closures: 1st Avenue is closed from Highway 14 to Elm Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. Temporary access is being provided as required to buildings without side or back doors in the downtown area. The base layer of pavement and nearly all concrete work is done from St. Mary’s Street to Elm Street. Curb and gutter is complete from St. Mary’s Street down to Highway 14. Crews are working on getting the base layer of pavement done from Elm to the railroad tracks done today while the block between the railroad and Highway 14 is being prepped for pavement also. South of Highway 14, crews are working on getting the street ready for gravel. Once the pavement is complete in an area, crews will come back and finish the sidewalks and driveways. In areas where all the sidewalk is complete, topsoil placement and sodding prep has begun. Concrete work is expected continue with curb and gutter on the last block south of Highway 14 next week along with sidewalks and driveways from Elm Street to Highway 14. The block between the railroad tracks and Highway 14 is also planned to be paved next week. If the weather allows, all paving and concrete work is expected to be finished within the first week or two of November.
Weekly Update – 10/14/21 Road Closures: 1st Avenue is closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. Sidewalk removals will begin early next week in downtown areas. Temporary access will be provided as required to buildings without side or back doors. All of the main underground utility work is complete for the project. The last thing to go in will be the 6” drain tile in the 2 downtown blocks from Walnut Street to Oak Street. This will be installed right before the street is graveled and will be located directly behind the new curb. 1st Avenue is now paved from St. Mary’s Street to just north of Elm Street. Work on sidewalks and driveways in this section is underway and should be complete on or before Monday. 1st Avenue is now graveled and has new curb and gutter form Elm to the railroad tracks. Starting next week, this area will be tolerance for paving. Paving from Elm to the railroad tracks may happen as soon as next Friday. Topsoil and sodding work may begin the week of October 25th. Crews expect to have the block from the railroad tracks to Highway 14 all graveled and ready for concrete sometime next week. After that block is done, the crews will jump to the south side of Highway 14. That is when the remaining sidewalk on the block south of Highway 14 will be removed as crews grade road and prepare for gravel.
Weekly Update – 10/8/21 Road Closures: 1st Avenue is closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. Sidewalk removals will begin early next week in downtown areas. Temporary access will be provided as required to buildings without side or back doors. On 1st Avenue, all of the main underground utility work is complete. The few items left include water services hook ups from Highway 14 to Walnut Street and 6” drain tile in the 2 downtown blocks from Walnut Street to Oak Street. 1st Avenue is now graveled from St. Mary’s Street to the railroad tracks. Crews have begun tolerancing the gravel for paving from St. Mary’s Street to Elm Street. This paving is expected to happen on Tuesday. Crews will also be jumping to south of the railroad tracks to begin prepping those areas for gravel. Later next week, crews will come back to complete the next round of concrete work. This will mainly include sidewalks and driveways in the areas where the curb and gutter is already in.
Weekly Update – 9/30/21 Road Closures: 1st Avenue is closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. In the downtown areas, sidewalk will be temporarily left in place where possible so that businesses can still get foot traffic to their buildings off 1st Avenue. On 1st Avenue, all of the underground utility work is complete from St. Mary’s Street to the railroad tracks. Only water services are left from the railroad tracks to Highway 14. Crews have been working this week on sewer and water mains from Highway 14 to Walnut Street, which is the last block of the project. Underground utility work is expected to finish within the next two weeks. This week, a crew began working on grading and graveling on 1st Avenue from Willow Street to Elm Street. They will continue to work their way south towards the railroad tracks. The street will then be ready for curb and gutter from St. Mary’s Street to the railroad tracks. The curb and gutter could be installed as soon as the middle of next week for this area. Once underground utilities are complete south of the railroad tracks, crews will be able to move in there to prepare the streets for gravel also.
Weekly Update – 9/23/21 Road Closures: 1st Avenue is closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. In the downtown areas, sidewalk will be temporarily left in place where possible so that businesses can still get foot traffic to their buildings off 1st Avenue. On 1st Avenue, all of the utility mains are complete from St. Mary’s Street to HWY 14. The new services should be hooked up on everything north of the railroad tracks first thing next week. On Monday, crews will begin to work on utilities south of HWY 14. Utilities are expected to be complete within the first week or two of October. Starting towards the middle of next week, crews will move in to start preparing the streets that are ready for gravel. This should be everything north of the railroad up to Willow. Willow to St. Mary’s is already graveled. Once this is all graveled, expect concrete to follow the week after, potentially the first week of October.
Weekly Update – 9/16/21 Road Closures: 1st Avenue is closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street and Willow Street are open, and Highway 14 will remain open at all times. In the downtown areas, sidewalk will be temporarily left in place where possible so that businesses can still get foot traffic to their buildings off 1st Avenue. On 1st Avenue, surface removals are complete now from the railroad tracks to Walnut Street. Utilities are complete from St. Mary’s Street to Elm Street and should be complete down to the railroad tracks near the end of next week. The watermain and casing pipe under the railroad is in and work is continuing on utilities south of the railroad tracks. Utility work will begin on the southside of Highway 14 as soon as the end of next week. The gravel surface is complete on 1st Avenue from St. Mary’s Street to Willow Street. As utilities are completed, the rest of the streets will be restored to a gravel surface. Concrete work will tentatively begin around the start of October. By then, all streets north of the railroad tracks will be graveled and should be ready for concrete.
Weekly Update – 9/9/21 Beginning on Sunday evening (9/12/2021), 1st Avenue will close in the downtown area from Walnut Street to Highway 14 and Highway 14 to the north. This road will not be open to traffic. Highway 14 will remain open at all times. Sidewalk will be temporarily left in place where possible so that businesses can still get foot traffic to their buildings off 1st Avenue. On 1st Avenue North, utility work has been progressing on schedule. Sanitary sewer and water mains are complete all the way from St. Mary’s Street to Rice Street. Services will be finished between Elm Street and Willow Street early next week and then will start from Elm Street to Rice Street after. Also starting next week will be the work underneath the railroad tracks. A new watermain and casing pipe will be augured underneath the tracks All utility work on 1st Avenue from St. Mary’s Street to Willow Street is complete. Crews have begun to put the street back together and are preparing to return it to gravel. Once more blocks are ready, crews will come in to start the concrete work. Road Closures: 1st Avenue will be closed from Highway 14 to Willow Street, and from Highway 14 to Walnut Street. The railroad crossing will be closed for the rest of the project. St. Mary’s Street is open, and Highway 14 will remain open at all times.
Weekly Update – 9/2/21 St. Mary’s Street is open to traffic. The only items left include sodding and reinstalling lighting. On 1st Avenue North, utility work has been moving along. Sanitary sewer and water mains are nearly complete all the way from St. Mary’s Street to Elm Street. By next week, mains will be complete all the way to Rice Street. Crews are currently installing sewer and water services right after the mains. With nearly all utilities complete north of Willow Street, crews will begin the process of getting 1st Avenue back to gravel from Willow Street to St. Mary’s Street starting next week. In the downtown area, removals will begin around either the end of next week or Sept. 13th from north of Highway 14 up to the railroad tracks. New watermain will be bored under the tracks around Sept. 15th. The downtown area south of Highway 14 will be the last area to be worked on. Road Closures: 1st Avenue is closed from Oak Street to Willow Street, and Willow Street to St. Mary’s Street. The railroad crossing on 1st Avenue will be closed for the rest of the project. 1st Avenue will close from Highway 14 to the railroad tracks as soon as the end of next week. St. Mary’s Street is open, and Highway 14 will remain open at all times.