The project is located throughout the city. It includes water main and water secondaries, sewer main and hookups, storm-sewer main and catch basins, curb and gutter, sidewalks, driveways, alleys and street surfaces.

Contractor:  MR Paving & Excavating

Weekly Updates

Update as of 11/5/2020

Work is nearly wrapped up for the year! The stretch of warm weather this week has helped us finish up basically all the seeding and other miscellaneous items. Outside of fixes and warranty work, next year will see the second and final layer of pavement going down on all the streets. There is no other significant work left, outside of paving, for this project next year.

Update as of 10/22/2020

Work is beginning to wrap up for the year. Paving is done and there is some topsoil placement and seeding left. The rest of the blocks that still need to be seeded will be dormant seeded once the snow melts. The second and final layer of pavement will be next year. Boulevard Restoration and Seeding: The following streets have been seeded. There may be some miscellaneous landscaping items that need to be completed on these streets yet.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
Topsoil Placement, Restoration, and Seeding Prep: The following blocks are in the process of being restored following concrete work and paving. Topsoil is being placed and conditioned prior to seeding. Any areas not seeded yet will be dormant seeded. Landscaping also needs to be completed on these streets this year.
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • Water Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
  Paving: The following streets are now done with concrete and paving this year. The second and final layer of pavement will be next year.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 2nd Avenue SE to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Water Street SW
  • Water Street SW, from HWY 4 to 1st Avenue S
  • 2nd Avenue SW, from Water Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Southdale Street SW to Remmele Street SW
  • Remmele Street SW, from Highway 4 to 4th Avenue SW
  • Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
The following streets are complete with all concrete and paving. All layers of pavement have been put on this year.
  • Southdale Street SW, from Highway 4 to 7th Avenue SW
  • Summit Street SW, from Highway 4 to 4th Avenue SW
  • Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • Alley, between 1st Ave N and 2ndAvenue NE, from Elm Street NE to Willow Street NE
  • Alley, between Water Street NE and Maple Street NE, from 1st Avenue S, to 2nd Avenue SE
Other Work: Outside of the paving, topsoil placement, and seeding work, there are few odds and ends to finish up once mother nature gives us some nicer weather. Some of these odds and ends include raising up gate valve box structures to the finish pavement grade for the year, reinstalling mailboxes and traffic signs, and installing the rest of the tracer wire access boxes. Landscaping items, such as pavers, rock, and retaining walls also need to be completed before the end of the year. Barricades and road closed signs will be removed as these and other odds and ends items are finished.

Update as of 10/16/2020

Work is beginning to wrap up for the year. The last gravel streets are being paved and the boulevards are being put back together. The rest of the blocks that still needed to be seeded will be dormant seeded. The second and final layer of pavement will be next year. Boulevard Restoration and Seeding: The following streets have been seeded.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
Topsoil Placement, Restoration, and Seeding Prep: The following blocks are in the process of being restored following concrete work and paving. Topsoil is being placed and conditioned prior to seeding. Any areas not seeded yet will be dormant seeded.
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • Water Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
Paving: The following streets are being paved today (10/16/2020). The second and final layer of pavement will be next year.
  • 2nd Avenue SW, from Water Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Southdale Street SW to Remmele Street SW
  • Remmele Street SW, from Highway 4 to 4th Avenue SW
  • Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
The following streets are now done with concrete and paving this year. The second and final layer of pavement will be next year.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 2nd Avenue SE to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Water Street SW
  • Water Street SW, from HWY 4 to 1st Avenue S
The following streets are complete with all concrete and paving. All layers have been put on this year.
  • Southdale Street SW, from Highway 4 to 7th Avenue SW
  • Summit Street SW, from Highway 4 to 4th Avenue SW
  • Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • Alley, between 1st Ave N and 2ndAvenue NE, from Elm Street NE to Willow Street NE
  • Alley, between Water Street NE and Maple Street NE, from 1st Avenue S, to 2nd Avenue SE
Other Work: Outside of the paving, topsoil placement, and seeding work, there are few odds and ends to finish up. Some of these odds and ends include raising up gate valve box structures to the finish grade for the year, reinstalling mailboxes and traffic signs, and installing the rest of the tracer wire access boxes. Landscaping items, such as pavers, rock, and retaining walls also need to be completed before the end of the year. Barricades and road closed signs will be removed as these and the other odds and ends items are finished.

Updated as of 10/8/2020

Work completed this week: Mathiowetz Construction placed gravel (class 5) on Elm Street and began to place it on St. Mary’s Street. Mathiowetz Construction also continued to construct edge drain on 12th Ave, and they completed the installation of a drain tile on the north side of Birch Street. Another item that began this week is placing topsoil back on top of disposal site one (east of 12th Ave). Work planned next: Mathiowetz construction plans to continue placing topsoil on disposal site one after it has been filled. Mathiowetz also plans to continue constructing the gravel base over the roadways on site. M.R. Paving and Excavation will be back to finish the water service connection for Home Cemetery.

Update as of 10/9/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, Kiefer Street NE and 3 blocks of Southdale Street SW. Three alleys will also be paved with the project. Boulevard Restoration and Seeding: The following streets have been seeded.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
Topsoil Placement and Seeing Prep: The following blocks are in the process of being restored following concrete work and paving. Topsoil is being placed and conditioned prior to seeding.
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • Water Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
Work in Progress: 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Base course paving is complete. Boulevard restoration is in progress.
  • The final layer of pavement will come next year.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The concrete patches are complete. The street should be patched in early next week.
Current Street, from 4th Avenue SW to HWY 4
  • The street has been graveled and the base course of pavement will go on today.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • Concrete work is complete. The street will begin to be shaped for pavement.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • The final layer of pavement will be going down today.
2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • The removals are now complete from Water Street to Walnut Street. The street will begin to be prepped for pavement.
Maple Street SW, from HWY 4 to 1st Avenue S
  • Removals are complete and the street will begin to be prepped for pavement.
Water Street SW, from HWY 4 to 1st Avenue S
  • The street has been paved with the first lift. The second and final layer is planned to go down next year.
Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • The final layer of pavement is expected to go down early next week.
Alley, between 1st Ave N and 2ndAvenue NE, from Elm Street NE to Willow Street NE
  • The first layer of pavement is going down today. The final layer of pavement is expected to go down early next week.
Alley, between Water Street NE and Maple Street NE, from 1st Avenue S, to 2nd Avenue SE
  • The first layer of pavement went down yesterday. The final layer is expected to go down early next week.

Update as of 10/1/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, Kiefer Street NE and 3 blocks of Southdale Street SW. Three alleys will also be paved with the project. Boulevard Restoration and Seeding: The following streets have been seeded.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 2nd Avenue SE to 3rd Avenue SW
  • Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
Topsoil Placement and Seeing Prep: The following blocks are in the process of being restored following concrete work and paving. Topsoil is being placed and conditioned prior to seeding.
  • Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • Water Street SW, from HWY 4 to 1st Avenue S
  • 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Current Street, from 4th Avenue SW to HWY 4
Work in Progress: 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Concrete work is in progress. The curb is in and the sidewalks and driveways are being poured.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The 2 concrete curb patches are complete. The pavement will be patched in as the crews come back for other street paving.
Current Street, from 4th Avenue SW to HWY 4
  • Concrete work is in progress. The curb is in and the sidewalks and driveways are being poured.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • The machine curb is in. As the flat work finishes up along 4th Ave NW, the crews will start working on Kiefer Street.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • All concrete work is complete. The base layer of pavement is complete, and the final layer is planned for the end of next week.
2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • The two blocks from Summit Street to Water Street are paved. Removals from Water Street to Walnut Street may begin next week.
Maple Street SW, from HWY 4 to 1st Avenue S
  • Concrete patch work is complete.
  • The street surface will be removed and reconstructed as the schedule and weather allow.
Water Street SW, from HWY 4 to 1st Avenue S
  • The old pavement has been removed and the gravel is currently being shaped for paving.
Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • The first layer of pavement is complete. The second layer is expected at the end of next week.
Alley, between 1st Ave N and 2ndAvenue NE, from Elm Street NE to Willow Street NE
  • The alley has been restored to gravel. There is a small section of concrete work to complete and then the alley will be shaped for paving
Alley, between Water Street NE and Maple Street NE, from 1st Avenue S, to 2nd Avenue SE
  • The existing alley surface was removed. It is being excavated and will be prepped for gravel base.

Update as of 9/18/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, Kiefer Street NE and 3 blocks of Southdale Street SW. Three alleys will also be paved with the project. Boulevard Restoration and Seeding:
  • The following streets are currently in the process of being seeded.
  • Summit Street from 3rd Avenue SW to 5th Avenue SE
  • Second Avenue SW, from Southdale Street to Summit Street.
  • Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
Topsoil Placement and Seeing Prep: The following blocks are in the process of being put back together following concrete work and paving. Topsoil is being placed and conditioned prior to seeding.
  •  Third Avenue NE, from HWY 14 to Oak Street NE
  • North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  •  East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • 2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Maple Street SW, from HWY 4 to 1st Avenue S
  • Water Street SW, from HWY 4 to 1st Avenue S
Work in Progress: 4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is complete. The street is currently being prepped for gravel, which will likely begin next week.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Utility construction is complete. The street will be patched with gravel until pavement work begins in the area.
Current Street, from 4th Avenue SW to HWY 4
  • The street has been graveled. The next step will be to begin concrete work.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • The street has been restored to gravel.
  • The storm sewer manhole has been replaced and the street is ready for concrete work to begin.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • All concrete work is complete. The base layer of pavement is going down today (9-18-20).
2nd Avenue SW, from Summit Street SW to Walnut Street SW
  • Concrete patch work is complete.
  • Two blocks from Summit Street to Water Street are being paved today (9-18-20).
Maple Street SW, from HWY 4 to 1st Avenue S
  • Concrete patch work is complete.
  • The street surface will be removed and reconstructed as the schedule and weather allow.
Water Street SW, from HWY 4 to 1st Avenue S
  • Concrete patch work is complete.
  • The street surface will be removed and reconstructed as the schedule and weather allow.
Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • The first layer of pavement is complete. The second layer is expected soon.
Alley, between 1st Ave N and 2ndAvenue NE, from Elm Street NE to Willow Street NE
  • Storm sewer reconstruction is complete. The alley will be restored to gravel once the streets by the hospital are ready to be opened.
Looking Forward: Alley, between Water Street NE and Maple Street NE, from 1st Avenue S, to 2nd Avenue SE
  • This alley will be paved. The concrete apron off of 1st Ave S was reconstructed.

Update as of 9/3/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, Kiefer Street NE and 3 blocks of Southdale Street SW. Three alleys will also be paved with the project. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Second Avenue SW, from Southdale Street to Summit Street.
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Third Avenue NE, from HWY 14 to Oak Street NE
  • The first layer of pavement is now complete. Topsoil and boulevard restoration is the next step.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The first layer of pavement is now complete. Topsoil and boulevard restoration is the next step.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • The first layer of pavement is now complete.
  • The rest of the concrete work will resume next week followed by boulevard restoration.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • The first layer of pavement is now complete.
  • The rest of the concrete work will resume next week followed by boulevard restoration.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • The first layer of pavement is now complete.
  • The rest of the concrete work will resume next week followed by boulevard restoration.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement is planned to be going down next year.
4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is wrapping up. The next step is to prepare the street for gravel.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • Utility construction is complete. The street will be patched with gravel until pavement work begins in the area.
Current Street, from 4th Avenue SW to HWY 4
  • The street has been graveled. The next step will be to begin concrete work.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • The removals are complete, and the street has been restored to gravel.
  • A storm manhole will be replaced prior to concrete work.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • Curb and gutter construction has begun and utility work is almost complete. The work in this area will be done in phases to maintain for business access.
Looking Forward: Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • The rest of this alley will be paved. Initial grading and graveling is complete and will be paved shortly.
Alley, between 1st Ave N and 2nd, from Elm Street NE to Willow Street NE
  • Storm sewer reconstruction has begun. A new intake will be created and

Update as of 8/26/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, Kiefer Street NE and 3 blocks of Southdale Street SW. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Final topsoil grading has started. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Second Avenue SW, from Southdale Street to Summit Street.
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement will go down next year.
Third Avenue NE, from HWY 14 to Oak Street NE
  • The street has been restored to gravel and the last concrete work will be complete this week.
  • Shaping for paving has started.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel and concrete work is complete.
  • Shaping for paving has started.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Concrete work is currently in progress. Once complete, the street can be prepped for pavement.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Concrete work is currently in progress. Once complete, the street can be prepped for pavement.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Concrete work is currently in progress. Once complete, the street can be prepped for pavement.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Final topsoil grading is starting. Seeding may begin next week.
  • The second layer of pavement is planned to be going down next year.
4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up and gravel prep will follow.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The boring is complete from 4th Ave NW to Alison Parkway. As other watermain is completed and ready for use, the last connection will be made.
Current Street, from 4th Avenue SW to HWY 4
  • The street is currently being prepped for gravel and should be graveled by the end of the week.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • The removals are complete, and the street has been restored to gravel.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • Curb and gutter construction has begun. The work in this area will be done in phases to allow for business access.
Looking Forward: Alley, between 1st Ave S and 2nd Ave SW, from Southdale St SW to Remmele St SW
  • The rest of this alley will be paved. Initial grading and graveling may begin soon as crews finish up in other areas.

Update as of 8/20/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW, and Kiefer Street NE. Work is expected to start next week on 3 blocks of Southdale Street SW. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Preliminary topsoil work has started. The final topsoil layer placement will begin next week followed shortly by seeding.
  • The second layer of pavement will go down next year.
Second Avenue SW, from Southdale Street to Summit Street.
  • Preliminary topsoil work has started. The final topsoil layer placement will begin next week followed shortly by seeding.
  • The second layer of pavement will go down next year.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer placement will begin next week followed shortly by seeding.
  • The second layer of pavement will go down next year.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer placement will begin next week followed shortly by seeding.
  • The second layer of pavement will go down next year.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer placement will begin next week followed shortly by seeding.
  • The second layer of pavement will go down next year.
Third Avenue NE, from HWY 14 to Oak Street NE
  • The street has been restored to gravel and the last concrete work will be complete next week.
  • The next step is to shape and prep the street for paving.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel and concrete work is complete.
  • The next step is to shape and prep the street for paving.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is ready for concrete work to begin next week.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is ready for concrete work to begin next week.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Both the East and West Frontage Roads have been restored to gravel and are ready for concrete work next week.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • All concrete patch work is complete, and the first layer of pavement is down.
  • The second layer of pavement is planned to be going down next year.
4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The boring is complete from 4th Ave NW to Alison Parkway. As other watermain is completed and ready for use, the last connection will be made.
Current Street, from 4th Avenue SW to HWY 4
  • Services are currently being hooked up. Once done, prep work for gravel will begin.
Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • The removals are complete, and the street has been restored to gravel.
Looking Forward: Southdale Street SW, from Highway 4 to 7th Avenue SW
  • This street will consist of a surface rehabilitation. The old pavement will be removed and reconstructed. Curb in gutter in disrepair will also be fixed.

Update as of 8/13/2020

Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Preliminary topsoil work has started. The final topsoil layer will come prior to seeding.
  • The second layer of pavement will go down next year.
Second Avenue SW, from Southdale Street to Summit Street.
  • Preliminary topsoil work has started. The final topsoil layer will come prior to seeding.
  • The second layer of pavement will go down next year.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer will come prior to seeding.
  • The second layer of pavement will go down next year.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer will come prior to seeding.
  • The second layer of pavement will go down next year.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Preliminary topsoil work has started. The final topsoil layer will come prior to seeding.
  • The second layer of pavement will go down next year.
Third Avenue NE, from HWY 14 to Oak Street NE
  • The street has been restored to gravel and concrete work is complete.
  • The next step is to shape and prep the street for paving.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel and concrete work is complete.
  • The next step is to shape and prep the street for paving.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is almost ready for concrete work to begin.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is almost ready for concrete work to begin.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • The West Frontage Road has been put back to gravel now that the utilities are complete.
  • The East Frontage Road has been cut to grade and ready for gravel. The drain tile is currently being installed and street will begin to be graveled after that is complete.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • All concrete patch work is complete, and the first layer of pavement is down.
  • The second layer of pavement is planned to be going down next year.
4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The boring is complete from 4th Ave NW to Alison Parkway. As other watermain is completed and ready for use, the last connection will be made and the new hydrant will be installed on the west end of the street.
Current Street, from 4th Avenue SW to HWY 4
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up.

Looking Forward:

Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • Removals are expected to begin early next week.
  • This block will consist of a complete surfacing reconstruct. There is no utility work planned for this segment.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • This street will consist of a surface rehabilitation. The old pavement will be removed and reconstructed. Curb in gutter in disrepair will also be fixed.

Update as of 8/7/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads, 3 blocks of 4th Avenue NW, 1 block of Current Street NW, and a portion of Elm Street NW

Work in Progress:

Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Concrete work and the base layer of paving is complete. The next step is to restore the boulevards and prepare for topsoil and seeding.
  • The second layer of pavement will go down next year.
Second Avenue SW, from Southdale Street to Summit Street.
  • Concrete work and the base layer of paving is complete. The next step is to restore the boulevards and prepare for topsoil and seeding.
  • The second layer of pavement will go down next year.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Concrete work and the base layer of paving is complete. The next step is to restore the boulevards and prepare for topsoil and seeding.
  • The second layer of pavement will go down next year.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Concrete work and the base layer of paving is complete. The next step is to restore the boulevards and prepare for topsoil and seeding.
  • The second layer of pavement will go down next year.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Concrete work and the base layer of paving is complete. The next step is to restore the boulevards and prepare for topsoil and seeding.
  • The second layer of pavement will go down next year.
Third Avenue NE, from HWY 14 to Oak Street NE
  • The street has been restored to gravel and concrete work is complete.
  • The next step is to shape and prep the street for paving.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel and concrete work is complete.
  • The next step is to shape and prep the street for paving.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is almost ready for concrete work to begin.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • The street has been restored to gravel and is almost ready for concrete work to begin.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • The West Frontage Road has been put back to gravel now that the utilities are complete.
  • Now that the bacteria test on the East Frontage Road passed, the water services can be hooked up. The street will then be cut to grade and prepped for gravel.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • All concrete patch work is complete, and the first layer of pavement is down.
  • The second layer of pavement is planned to be going down next year.
4th Avenue SW, from Rice Street SW to Allison Parkway
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up.
Elm Street NE, from 4th Avenue SW to Allison Parkway
  • The boring is complete from 4th Ave NW to Alison Parkway. As other watermain is completed and ready for use, the last connection will be made and the new hydrant will be installed on the west end of the street.
Current Street, from 4th Avenue SW to HWY 4
  • Utility construction is in progress. As the utility construction is completed, services will be hooked up.

Looking Forward:

Kiefer Street NE, from 2nd Avenue NE to 3rd Avenue NE
  • This block will consist of a complete surfacing reconstruct. There is no utility work planned for this segment.
Southdale Street SW, from Highway 4 to 7th Avenue SW
  • This street will consist of a surface rehabilitation. The old pavement will be removed and reconstructed. Curb in gutter in disrepair will also be fixed.

Update as of 7/23/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads.

Work in Progress:

Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Concrete work is done on all blocks of this segment.
  • Paving is complete on Summit SE from 1st Avenue S to 5th Avenue SE. The next step will be boulevard restoration.
  • The last two blocks will begin to be prepped for blacktop.
Second Avenue SW, from Southdale Street to Summit Street.
  • Concrete work is done on all blocks of this segment.
  • Paving is complete on the block between Remmele Street SW and Brackenridge Street SW.
  • The other blocks will begin to be prepped for blacktop.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Concrete work is done on all blocks of this segment.
  • Paving is complete on the block between Highway 4 and 2nd Avenue SW.
  • The other block and the intersection will continue to be prepped for blacktop.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Concrete work and blacktop paving are done on all blocks of this segment.
  • The next step will be boulevard restoration.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Concrete work is complete on this block and the street will begin to be prepped for gravel.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Utilities are complete and the street will begin to be graveled soon.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel. The next step is to prepare for concrete.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Utilities are complete now. The street will begin to be prepared for gravel.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Utilities are complete now. The street will begin to be prepared for gravel.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Utility construction is in progress. Mains are almost complete, and services are also being hooked up.
  • As they finish up with utilities, the roads will begin to be restored to gravel.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Pavement removals are complete. The north leg down to Carrol Street has been restored to gravel. The area south of Carrol Street is currently being prepped for gravel.

Looking Forward:

4th Avenue SW, from Rice Street SW to Allison Parkway Elm Street NE, from 4th Avenue SW to Allison Parkway Current Street, from 4th Avenue SW to HWY 4
  • Removal of the street surface will begin early next week. These streets consist of new watermain, sanitary sewer, and some storm sewer.

Update as of 7/17/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads.

Work in Progress:

Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • Concrete work is done on all blocks of this segment.
  • Paving was completed today on Summit SE from 1st Avenue S to 5th Avenue SE. The next step will be boulevard restoration.
  • The last two blocks will begin to be prepped for blacktop.
Second Avenue SW, from Southdale Street to Summit Street.
  • Concrete work is done on all blocks of this segment.
  • Paving was completed today on the block between Remmele Street SW and Brackenridge Street SW.
  • The other blocks will begin to be prepped for blacktop.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Concrete work is done on all blocks of this segment.
  • Paving was completed today on the block between Highway 4 and 2nd Avenue SW.
  • The other block and the intersection will continue to be prepped for blacktop.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Concrete work and blacktop paving are done on all blocks of this segment.
  • The next step will be boulevard restoration.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • Concrete work is complete on this block and the street will begin to be prepped for gravel.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Utilities are complete and the street is currently being prepped for gravel.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • The street has been restored to gravel. The next step will be to compact the gravel and prepare for concrete.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Mainline utilities are complete. Services hook ups will follow once the required testing is finished.
  • The street will begin to be prepared for gravel after services are complete.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Mainline utilities are complete. Services hook ups will follow once the required testing is finished.
  • The street will begin to be prepared for gravel after services are complete.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Utility construction is in progress. Once all the utility mains are complete, services can be hooked up.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Pavement removals are complete. The street is being sub-cut and tiled and will begin to be prepped for granular foundation and then gravel.

Looking Forward:

4th Avenue SW, from Rice Street SW to Allison Parkway Elm Street NE, from 4th Avenue SW to Allison Parkway Current Street, from 4th Avenue SW to HWY 4
  • Work will begin in a couple weeks in this area. These streets consist of new watermain, sanitary sewer, and some storm sewer.

Update as of 7/9/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 1 block of 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE, 1 block of Brackenridge Street SE, the HWY 4 East Frontage Road and West Frontage Roads. Work in Progress:
  • Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • The curb and gutter, sidewalks, and driveways are complete between 1st Avenue S and 4th Avenue SE. These blocks will begin to be prepped for blacktop pavement.
  • Topsoil is being added on Summit Street SE where concrete is done. This will be rough graded only until everything is ready for seeding.
  • The two blocks of Summit SW are now graveled. They will begin to be prepped for concrete work.
Second Avenue SW, from Southdale Street to Summit Street.
  • All utility main line and services are complete.
  • The south three blocks from Southdale to Burnside are all graveled and the last block between Brunside and Summit will be graveled by the end of the week.
  • The two blocks form Southdale to Brackenridge are now complete with concrete work. The next step is to prepare for blacktop pavement.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Curb and gutter, sidewalks, and driveways are now complete on the two blocks. Next, they will start prepping for blacktop pavement.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • Curb and gutter, sidewalks, and driveways are now complete. Next, they will start prepping for blacktop pavement.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • This street is being prepped for concrete work.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Utilities are now complete. The street will begin to be prepped for gravel. In order to maintain access to the elevator, this street will not be complete till North Street is graveled.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Utilities are complete. The street will start to be prepped for gravel next week. Once the street is returned to gravel, the crews will move into 3rd Avenue NE. This is done to maintain access to the elevator.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Mainline utilities are complete. Services hook ups will follow once the required testing is finished.
  • The street will begin to be prepared for gravel after services are complete.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Mainline utilities are complete. Services hook ups will follow once the required testing is finished.
  • The street will begin to be prepared for gravel after services are complete.
East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Watermain construction has started on the East Frontage Road while storm sewer construction is beginning on the West Frontage Road.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Curb and gutter repairs are finished. Pavement removal and reconstruction may begin on part of the street starting next week.
Looking Forward: 4th Avenue SW, from Rice Street SW to Allison Parkway Elm Street NE, from 4th Avenue SW to Allison Parkway Current Street, from 4th Avenue SW to HWY 4
  • Work will begin in a couple weeks in this area. These streets consist of new watermain, sanitary sewer, and some storm sewer.

Update as of 6/25/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 3rd Avenue NE, North Street NE, 1 block of Remmele Street SE and 1 block of Brackenridge Street SE. Work is expected to start on the two frontage roads on HWY 4 by the lake starting next week. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • The curb and gutter, sidewalks, and driveways are complete on 3 of the 4 blocks between 1st Avenue S and 4th Avenue SE. Only sidewalk is left on the last block of Summit SE between 4th and 5th Avenue SE.
  • Topsoil is being added on Summit Street SE where concrete is done. This will be rough graded only until everything is ready for seeding.
  • Utility work on the two blocks of Summit SW is complete. These two blocks are being prepped for gravel.
Second Avenue SW, from Southdale Street to Summit Street.
  • All utility main line and services are complete.
  • The south three blocks from Southdale to Burnside are all graveled as of today. The last block is being prepped and will be graveled soon.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Both blocks are now graveled and being prepped for concrete work.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • The street has been restored to gravel. The next step is to prepare the streets for concrete work.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • The street has been restored to gravel. The next step is to prepare the streets for concrete work.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Watermain is now complete and storm sewer work is currently in progress.
  • Once the mainline utilities are done, the water services can be hooked up and then the street will begin to be prepared for gravel.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Utilities will be complete by the end of the week. After that, the street can be prepped for a gravel base as crews make their way north.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • The waterman is complete and storm sewer mainline construction is in progress. Water services will be hooked up once all the main line is complete.
  • The street will begin to be prepared for gravel after utilities are complete.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Removals on the street are complete and utility construction has started.
  • The tie-ins to the existing utilities at the intersection of Brackenridge Street SE and 2nd Avenue SE are just about complete and mainline utilities down the street will follow.
  • This block will have the existing watermain, storm sewer, and sanitary sewer reconstructed.
Looking Forward:
  • East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Gas lines were recently relocated in both these blocks to avoid utility conflicts.
  • Removals are expected to start early next week.
  • Work in these blocks will consist of watermain, sanitary sewer, and partial storm sewer construction.
  • The street will be reconstructed, and curb and gutter will be constructed on both sides of each street.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Curb and gutter repairs are finished. Pavement removal and reconstruction will begin at a later date.

Update as of 6/18/2020

Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • The curb and gutter, sidewalks, and driveways are complete on 3 of the 4 blocks between 1st Avenue S and 4th Avenue SE. Only sidewalk is left on the last block of Summit SE between 4th and 5th Avenue SE.
  • Topsoil is being added on the Summit Street SE where concrete is done. This will be rough graded only and stay rough graded until everything is ready for seeding.
  • The two blocks of Summit SW are done with utility work. These will begin to be graveled as the crews work their way north in the area.
Second Avenue SW, from Southdale Street to Summit Street.
  • All utility main line and services are complete. These blocks are in the process of getting prepped for gravel.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Both blocks are now graveled and being prepped for concrete.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • The street has been restored to gravel. The next step is to prepare the streets for concrete.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • The street has been restored to gravel. The next step is to prepare the streets for concrete.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Watermain is now complete and storm sewer work is currently in progress.
  • Once the mainline utilities are done, the water services can be hooked up.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Storm sewer construction has started. Watermain construction will follow next week.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • Utility construction has started on this block. The waterman is currently being constructed and storm sewer will follow.
  • Once the storm sewer and watermain are complete, the water services can be hooked up and then gravel will follow.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • Removals on the street are complete and utility construction will begin shortly.
  • This block will have the existing watermain, storm sewer, and sanitary sewer reconstructed.
Looking Forward: East and West HWY 4 Frontage Roads, South of St. Mary’s Street
  • Work in these blocks will consist of watermain, sanitary sewer, and partial storm sewer construction.
  • The street will be reconstructed and curb and gutter will be constructed on both sides of each street.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Curb and gutter repairs are finished. Pavement removal and reconstruction will begin later.

Update as of 6/11/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, 3rd Avenue NE, and 6th Avenue NE. Looking ahead, work is expected to start on North Street beginning next week, along with 1 block of Remmele Street SE and 1 block of Brackenridge Street SE. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • The curb and gutter, sidewalks, and driveways are complete on 3 of the 4 blocks between 1st Avenue S and 4th Avenue SE.
  • The block between 4th Ave SE and 5th Ave SE is graveled now and is currently being prepped for concrete work, which will likely begin early next week.
  • The watermain in the two blocks between HWY 4 and 1st Ave S are finished. The next step in these two blocks is to hook up water services.
Second Avenue SW, from Southdale Street to Summit Street.
  • The mainline utilities are complete. Utility services are currently being hooked up.
  • As the utility services are complete, M.R. will follow behind and prep the subgrade for gravel.
  • The block between Southdale and Remmele is graveled. Once it is prepped, concrete work can begin.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Both blocks are now graveled and being prepped for concrete.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • The subgrade is currently being prepped for gravel.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • The subgrade is currently being prepped for gravel.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • Curb and gutter repairs are finished. Pavement removal and reconstruction will begin at a later date.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Removals are complete and utility work has resumed. This block has both watermain and storm sewer.
Looking Forward: North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Removals are almost complete.
  • Work in this segment will include installing new watermain, storm sewer, adding curb and gutter, and paving the street.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed, and utility construction will start shortly after.
  • This block will have the existing watermain, storm sewer, and sanitary sewer reconstructed.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed, and utility construction will start shortly after.
  • This block will have the existing watermain and storm sewer reconstructed. There is no sanitary sewer in this block.

Update as of 6/4/2020

Work is currently being done in multiple areas of town: 6 blocks on Summit Street, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, 1 block on Burnside Street SW, and 6th Avenue NE. Work on 3rd Avenue NE but will be resuming next week. Looking ahead, work is expected to start on North Street beginning next week, and later, work will start on 1 block of Remmele Street SE and 1 block of Brackenridge Street SE. Work in Progress: Summit Street, from 3rd Avenue SW to 5th Avenue SE.
  • The curb and gutter, sidewalks, and driveways are complete on 3 of the 4 blocks between 1st Avenue S and 4th Avenue SE.
  • The block between 4th Ave SE and 5th Ave SE is graveled now and is currently being prepped for concrete work.
  • The watermain in the two blocks between HWY 4 and 1st Ave S are finished. The next step in these two blocks is to hook up water services.
Second Avenue SW, from Southdale Street to Summit Street.
  • The mainline utilities are almost complete. There is one block of sanitary sewer to finish up and then after that, the utility services can be hooked up.
  • As the utility services are complete, M.R. will follow behind and prep the subgrade for gravel.
  • The block between Southdale and Remmele was just graveled. Once it is prepped, concrete work can begin.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • Removals on the west block will begin in the next few working days.
  • The east of the two blocks is graveled and is just starting to be prepped for concrete.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • The utility work in these blocks are complete. The next step is to begin prepping the subgrade for gravel.
Burnside Street SW, from 2nd Avenue SW to 3rd Avenue SW
  • The utility work in these blocks are complete. The next step is to begin prepping the subgrade for gravel.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • The service repairs in the street are complete. The holes opened for the service repairs have been temporarily patched in and graveled over.
  • Curb and gutter removals have started for the areas to be repaired. The repairs are expected to start next week.
Looking Forward: Third Avenue NE, from HWY 14 to Oak Street NE
  • Removals are expected to start early next week. Once removals are done, utility construction can resume on the south portion of the block.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Removals are expected to start early next week.
  • Work in this segment will include installing new watermain, storm sewer, adding curb and gutter, and paving the street.
Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed, and utility construction will start shortly after.
  • This block will have the existing watermain, storm sewer, and sanitary sewer reconstructed.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed, and utility construction will start shortly after.
  • This block will have the existing watermain and storm sewer reconstructed. There is no sanitary sewer in this block.

Update as of 5/28/2020

Work is currently being done in multiple areas of town: 4 blocks on Summit Street SE, 4 blocks on 2nd Avenue SW, 2 blocks on Remmele Street SW, 2 blocks on Brackenridge Street SW, and 1 block on Burnside Street SW. Work is done for the moment on 6th Avenue NE and 3rd Avenue NE but will be resuming at a later date. Looking ahead, work is expected to start on 2 blocks of Summit Street SW, 1 block of Remmele Street SE and 1 block of Brackenridge Street SE Work in Progress: Summit Street SE, from 1st Avenue South to 5th Avenue SE.
  • As of today, the curb and gutter, sidewalks, and driveways are complete on 3 of the 4 blocks between 1st Avenue S and 4th Avenue SE.
  • Once the last block is dry and prepared, M.R. will begin to place gravel and prep for concrete.
Second Avenue SW, from Southdale Street to Summit Street.
  • The mainline sanitary sewer and watermain are complete in 2 of the 4 blocks, from Southdale to Brackenridge. Sanitary and water services are connected in the first block from Southdale to Remmele Street.
  • The next step is to continue constructing mainline sewer and water up to Summit Street. Once the mainlines are complete, the crews will jump back and start the utility services.
  • As the utility services are complete, M.R. will follow behind and prep the subgrade for gravel.
Remmele Street, from 1st Avenue S to 3rd Avenue SW
  • The watermain is complete in this segment.
  • R. has started grading and prepping for gravel. Removals on the west of the two blocks will happen as the street is constructed.
Brackenridge Street SW, from 1st Avenue S to alley between 2nd Avenue SW & 3rd Avenue SW
  • This segment consists only of watermain for utilities. The east block of watermain is complete as of today. The ½ block will be completed soon.
  • There are no services in this block so as the main is completed, the street will start to get prepped for gravel.
Burnside Street SW, from 2nd Avenue SW to HWY 4
  • Like Brackenridge Street, this segment also has just watermain for utilities. The watermain has been connected to the existing pipes at the ends of the block.
  • Holtmeier Construction will continue to install the rest of the main on this street as they work their way north in the area.
Looking Forward: Brackenridge Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed and utility construction will start shortly after.
  • This block will have the existing watermain, storm sewer, and sanitary sewer reconstructed.
Remmele Street, from 1st Avenue S to 2nd Avenue SE
  • As utilities are getting finished on the other blocks in the area, the existing street surface will be removed and utility construction will start shortly after.
  • This block will have the existing watermain and storm sewer reconstructed. There is no sanitary sewer in this block.
Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE
  • The service repairs in the street are complete. The holes opened for the service repairs have been temporarily patched in and graveled over. Currently, work is done in the area but will resume at a later date with the street reconstruction.
Third Avenue NE, from HWY 14 to Oak Street NE
  • Currently, work is complete in this area. Construction will resume as utilities are finished at the areas in the south end of town.
North Street NE, from 5th Avenue NE to 6th Avenue NE
  • Construction in this area will begin as the areas on the south end of town are finished and around the same time as Third Avenue NE.
Work in this segment will include installing new watermain, storm sewer, adding curb and gutter, and paving the street.

Update as of 5/15/2020

Work is currently being done in three different areas of town: 4 blocks on Summit Street SE, 1 block on Third Avenue NE and 4 blocks split between Second Avenue SW and Remmele Street SW. Some work may also start soon on Sixth Avenue NE. Summit Street SE, from 1st Avenue South to 5th Avenue SE • Over the last week, M.R. Paving & Excavating has been working the subgrade to achieve a uniform and solid base to start building the road. • Once the subgrade has achieved the desired compaction, drain tile is placed along each edge of the street to help keep water out. • As soon as the edge drain is installed, gravel will be hauled in to start building the road base. O Third Avenue NE, from Main Street East to Oak Street NE • The main push to finish the watermian by the water tower is finished. Once the watermain is tested, Holtmeier Construction will make the final connections. • Their work in the south portion of the street will resume later. Second Avenue SW from Southdale Street to Brackenridge Street, and Remmele Street from 1st Avenue S to 3rd Avenue SW • The watermain is finished in this area. The sanitary sewer is currently under construction. • Once the mains are completed, the crew will go back to hook up water and sanitary services. • The other block of Remmele will also have its pavement and concrete removed after the utility mains are installed. Subgrade preparation will begin after removals are completed. Sixth Avenue NE, from St. Mary’s Street to 3rd Ave NE • The initial work in this area will consist of repairing the old connections from the individual water services to the watermain in the street. • Once the repairs are done, the street will be patched in with gravel until it’s time to start reconstruction of the entire street.