City of Waconia, Waconia Parkway South Improvement Project
Top
 

Project Updates

The project has been substantially completed. Punchlist work and minor repair work will occur in the spring as necessary. This will be the final update for this project, and the project website will be discontinued on December 1st.  Thank you for your patience during the construction of this important project.

Project Updates

October 12, 2022

The roadway is now open! Please travel safely through the corridor as electrical and restoration work will be ongoing.  Thank you for your patience during the construction of this project!

October 7, 2022

Due to an unexpected delay with roadway striping, the roadway is now expected to reopen on Monday, October 10th. We apologize for the inconvenience and appreciate your patience as we work to complete this project!

October 7, 2022

This week additional signing, electrical, and lighting work were completed. The final paving was completed this past Monday, with striping scheduled to be completed yesterday and today. Therefore, the roadway is planned to be opened prior to this weekend. Please note that some restoration and cleanup items will be occurring after the roadway is open. Also, the manufacturing of the decorative metal railings to be placed on top of the retaining walls adjacent to the sidewalk and trail have been delayed. Therefore, temporary fencing will be placed in these locations until the permanent metal railings are able to be installed.

September 30, 2022

This week electrical wiring and placement of the light pole bases for trail lighting along with misc. restoration items were completed. Paving and striping are scheduled for next week. Remaining work then includes sign installations, installation of light poles, removal of traffic control devices, and misc. site restoration and cleanup items.