13th St, Grace Ave & Rice Ave Improvements
Proposed Improvements
- asphalt streets with concrete curb and gutter
- concrete driveway aprons
- sanitary sewer system
- water main, hydrants and water services
- storm sewer system
Construction is anticipated to begin May 2024!
Project Update – July 19, 2024
Week of July 22
- Phase 2A
- Complete driveway and sidewalk construction
- Phase 2B
- Complete sewer and water service construction
- Phase 3C
- Complete sanitary sewer construction
- Begin sewer and water service construction
Week of July 29
- Phase 2B
- Begin road base construction in preparation for gravel installation
- Phase 3C
- Complete sewer and water service construction
- Complete storm sewer construction
Garbage & Recycling: Residents should label their garbage & recycling bins with their house number by using a piece of tape and marker. Residents should bring bins to the end of their driveway the evening prior to pick-up to ensure that the bins are brought to the appropriate pick-up location by the contractor. The Contractor will move bins the morning of the scheduled garbage and recycling pick-up dates and return the bins in the evening.
Project Contacts
On-Site Construction Project Representative
Nate Thein
Bolton & Menk, Inc.
320-979-9070
Nate.Thein@bolton-menk.com
Project Engineer
Mitchell Lease
Bolton & Menk, Inc.
320-441-9146
Mitchell.Lease@bolton-menk.com