13th St, Grace Ave & Rice Ave Improvements

Proposed Improvements

  • asphalt streets with concrete curb and gutter
  • concrete driveway aprons
  • sanitary sewer system
  • water main, hydrants and water services
  • storm sewer system

Construction is anticipated to begin May 2024!

Project Update – July 19, 2024

Week of July 22

  • Phase 2A
    • Complete driveway and sidewalk construction
  • Phase 2B
    • Complete sewer and water service construction
  • Phase 3C
    • Complete sanitary sewer construction
    • Begin sewer and water service construction

Week of July 29

  • Phase 2B
    • Begin road base construction in preparation for gravel installation
  • Phase 3C
    • Complete sewer and water service construction
    • Complete storm sewer construction

Garbage & Recycling: Residents should label their garbage & recycling bins with their house number by using a piece of tape and marker. Residents should bring bins to the end of their driveway the evening prior to pick-up to ensure that the bins are brought to the appropriate pick-up location by the contractor. The Contractor will move bins the morning of the scheduled garbage and recycling pick-up dates and return the bins in the evening.

Contractor

Duininck, Inc of Prinsburg, MN

Documents

May Newsletter

Project Newsletter

Sign Up for Project Updates

What to Expect During Construction

Project Contacts

On-Site Construction Project Representative

Nate Thein
Bolton & Menk, Inc.
320-979-9070
Nate.Thein@bolton-menk.com

Project Engineer

Mitchell Lease
Bolton & Menk, Inc.
320-441-9146
Mitchell.Lease@bolton-menk.com