Top

13th St, Grace Ave & Rice Ave Improvements

Proposed Improvements

  • asphalt streets with concrete curb and gutter
  • concrete driveway aprons
  • sanitary sewer system
  • water main, hydrants and water services
  • storm sewer system

Construction is anticipated to begin May 2024!

Project Update – May 9, 2025

Construction for the 13th Street SW, Grace Avenue SW, and Rice Avenue SW Improvement Project is resuming for 2025.

Week of May 19

  • Remaining concrete repairs will be completed throughout the project area. Residents will be notified if it is anticipated that concrete replacement work will impact driveways.
  • Miscellaneous project work and clean-up throughout project area.

Week of June 2

  • Paving of the final layer of street pavement will be completed.
    • Notices will be handed out prior to paving with more information.

Residents are encouraged to begin watering grass 1-2 times per day for 10-15 minutes for best results. Additional seed will be added in areas where topsoil has been regraded.

There should be no impact to garbage/recycling and mail services.

Residents are encouraged to contact Nate Thein at 320-979-9070 with any items that need to be addressed prior to the completion of the project.

Contractor

Duininck, Inc of Prinsburg, MN

Documents

May Newsletter

Project Newsletter

Sign Up for Project Updates

What to Expect During Construction

Project Contacts

On-Site Construction Project Representative

Nate Thein
Bolton & Menk, Inc.
320-979-9070
Nate.Thein@bolton-menk.com

Project Engineer

Mitchell Lease
Bolton & Menk, Inc.
320-441-9146
Mitchell.Lease@bolton-menk.com