20th Street SE & 2nd Avenue SE Improvement Project

Proposed Improvements

The City of Willmar is undertaking a construction project to improve the city streets and utilities on 20th Street SE. The project includes road construction, sanitary sewer improvements, water system improvements, and storm sewer improvements.

Project Schedule

  • Mobilization of equipment, removals of existing pavement and temporary access points will be constructed the week of May 19th through May 30th, 2025
  • Sanitary sewer to be constructed the week of June 2nd
  • Watermain to be constructed the week of June 9th
  • Storm sewer and street construction will follow
  • Construction notices will be provided to residents throughout the project
  • Construction will be substantially complete by fall 2025

Project Updates

Check back for project updates!

Contractor

Kurilla Contracting
Buffalo, MN

Documents

June 2025 Construction Update

May 2025 Construction Update

Sign Up for Project Updates

Engineer Contacts

Dalton Lindstrand
On-Site Construction Representative, Bolton & Menk Inc.
(320)-894-3826
Dalton.Lindstrand@bolton-menk.com

Spencer Johnson
Project Manager, Bolton & Menk, Inc.
(320)-979-6136
Spencer.Johnson@bolton-menk.com

Contractor Contact

Josh Bridell
Kurilla Contracting
(763)-954-0152
josh@kurillacontracting.com