13th St, Grace Ave & Rice Ave Improvements

Proposed Improvements

  • asphalt streets with concrete curb and gutter
  • concrete driveway aprons
  • sanitary sewer system
  • water main, hydrants and water services
  • storm sewer system

Construction is anticipated to begin May 2024!

Project Update – July 3, 2024

Week of July 8:

  • Phase 2A
    • Concrete curb and gutter construction
  • Phase 2B
    • Complete storm sewer construction
    • Watermain construction
    • Begin sewer and water service construction
  • Phase 3A
    • Begin removal of existing road base material
  • Phase 3B
    • Complete watermain construction
    • Complete sanitary sewer construction
    • Begin sewer and water service construction

Week of July 15:

  • Phase 2A
    • Complete concrete driveway and sidewalk construction
  • Phase 2B
    • Continue sewer and water service construction
  • Phase 3A
    • Complete removal of existing road base material
    • Complete gravel installation
  • Phase 3B
    • Complete sewer and water service construction
    • Complete storm sewer construction

Garbage & Recycling: The Contractor will be moving bins during pick up days to a centralized location for pick up. We ask that all residents label their garbage can with their house number by using a piece of tape and marker. Pick up times may vary during construction, and we ask that residents please bring bins to the end of your driveway the evening prior to pick up.

Contractor

Duininck, Inc of Prinsburg, MN

Documents

May Newsletter

Project Newsletter

Sign Up for Project Updates

What to Expect During Construction

Project Contacts

On-Site Construction Project Representative

Nate Thein
Bolton & Menk, Inc.
320-979-9070
Nate.Thein@bolton-menk.com

Project Engineer

Mitchell Lease
Bolton & Menk, Inc.
320-441-9146
Mitchell.Lease@bolton-menk.com