Thompson Park Parking Lot & Ella Avenue Path

Parking Lot and Path Reconstruction

Proposed Improvements

The City of Willmar is planning to reconstruct Thompson Parking Lot and Ella Avenue Path. Construction is anticipated to begin May 2024.

Project Update – June 21, 2024

Week of 17:

  • Complete Tree Removals

Week of 24:

  • Complete removals of existing path and parking lot pavement
  • Begin gravel installation for parking lot and path

Week of June 1:

  • Complete gravel installation for parking lot and path
  • Complete paving for Ella Avenue path

Starting the week of June 24, the Thompson Park parking lot and Ella Avenue path will be closed to the public until construction is completed.

Contractor

Joe Riley Construction of Morris, MN

Documents

Project documents coming soon!

Sign Up for Project Updates

On-Site Construction Representative

Aidan Musser
Bolton & Menk, Inc.
320-737-1898
Aidan.Musser@bolton-menk.com

Project Engineer

Mitchell Lease
Bolton & Menk, Inc.
320-441-9146
Mitchell.Lease@bolton-menk.com