6th Street SW Reconstruction
Proposed Improvements
- 38-foot-wide asphalt street with concrete curb and gutter
- Concrete driveway aprons
- Sanitary sewer, manholes, and sewer services
- Water main, hydrants with isolation valves, mainline valves, and water services
- Storm sewer, storm manholes and catch basins
Project Update – April 25, 2024
We have worked diligently with the contractor to develop a plan to address the inadequate turf establishment areas throughout the project area.
The contractor has coordinated a schedule with a new seeding subcontractor to repair these areas throughout the project. The corrective work will include the application of weed killer/preventer, overseeding, and the application of hydromulch on the surface of the overseeded areas. The overseeding will be completed with spike seeding machinery, which will loosen the soil and embed the seed into the soil with fertilizer. It is recommended that residents and their pets stay off these areas for a minimum of 24-hours from application to avoid any potentially harmful effects from the weed treatment.
The seeding subcontractor plans to be onsite to complete the work either Friday, April 26 or early the week of April 29. The contractor will not be providing any maintenance of these areas after the overseeding is completed. Residents must water the lawns to properly establish the turf. Please follow the “Newly Seeded Lawns” management document to ensure the growth and development of the seeded areas.
Thank you for your patience and cooperation during the turf establishment process!
Contractor
Voss Pluming & Heating of Paynesville, Inc.
Documents
Sign Up for Project Updates
Project Contact
Spencer Johnson
Bolton & Menk, Inc.
320-979-6136
Spencer.Johnson@bolton-menk.com
City Engineer
Jared Voge
Bolton & Menk, Inc.
612-756-0326
Jared.Voge@bolton-menk.com