Top

Gorton Ave, 18th St & 20th St Improvements

Project Phasing Map

Proposed Improvements

  • asphalt streets with concrete curb and gutter
  • concrete driveway aprons
  • sanitary sewer system
  • water main, hydrants and water services
  • storm sewer system

Project Updates – April 8, 2024

The 2024 Construction season will be starting on the Gorton Avenue Improvement project soon. The Contractor is currently planning to complete the remaining work for the project by the end of June, 2024, and the anticipated schedule for the next 4 weeks is provided below:

All Phases

  • Week of April 15
    • Installation of traffic control devices/Gorton Avenue detour

Phases 1, 3, & 4

  • Week of April 29
    • Removals/Grading of new bituminous path on north side of Gorton Avenue
  • Week of May 6
    • Removals/Grading of new bituminous path on north side of Gorton Avenue (Continued)

Phase 2

  • Final topsoil grading and seeding of the boulevards is anticipated by the end of June.

Phase 5

  • Week of April 15
    • Pavement/surface removals
  • Week of April 22
    • Pavement/surface removals (Continued)
    • Underground utility construction
  • Week of April 29
    • Underground utility construction (Continued)
    • Removals/Grading of new bituminous path on north side of Gorton Avenue
  • Week of May 6
    • Finish underground utility construction
    • Start street base construction
    • Removals/Grading of new bituminous path on north side of Gorton Avenue (Continued)

Additional Notes:

Traffic: The construction area is closed to through-traffic and is open to local-traffic only.  A police presence will be in place periodically on Gorton Avenue and fines may be issued to traffic violators.

Garbage/Recycling: Residents are asked to label their garbage and recycling bins by writing their house number on a piece of tape and attaching it to their bins.  Place the bins near the street on pick-up days and the contractor will move them as needed for pick-up.

Punch List: If there are any items that you believe need to be addressed prior to the completion of the project, please contact Spencer Johnson at the contact information provided.

Additional updates will be provided as the construction progresses.
Thank you for your continual patience and understanding throughout the process of improving your streets and utilities! 

Contractor

Duininck Incorporated

Documents

Newsletter 1 – May 1, 2023

Sign Up for Project Updates

Sign up for email or text updates below!

What to Expect During Construction

Project Contact

Spencer Johnson
Bolton & Menk, Inc.
320-979-6136
Spencer.Johnson@bolton-menk.com

 

City Engineer

Jared Voge
Bolton & Menk, Inc.
612-756-0326
Jared.Voge@bolton-menk.com