Gorton Ave, 18th St & 20th St Improvements
Project Phasing Map
Proposed Improvements
- asphalt streets with concrete curb and gutter
- concrete driveway aprons
- sanitary sewer system
- water main, hydrants and water services
- storm sewer system
Project Updates – August 22, 2024
Construction is nearing completion for the Gorton Avenue Area Improvement project. The Contractor is planning to complete the remaining work for the project fall of 2024.
Phase 1 through 5:
Construction is nearing completion on the Gorton Avenue Area Improvement Project. Items remaining are as follows:
- Striping of traffic control lines
- Interior Lining of Storm Catch Basins
- Seeding touch-ups and rework.
- Sealing of the concrete street pavement on Gorton Avenue.
The contractor will be on site to complete punchlist work through the remainder of August and September.
- If there are any items that you believe need to be addressed prior to the completion of the project, please contact Spencer Johnson at the contact information provided.
Additional Notes:
Traffic: The detour for Gorton Avenue and all traffic control devices have been removed from site. Traffic has returned to normal with slight delays as the contractor is on site completing punchlist items.
Turf Establishment: After the seeding is completed, it is the residents’ responsibility to maintain the lawn. Residents must water the lawns to properly establish the turf. Please follow the “Newly Seeded Lawns (LINK)” management document to ensure the growth and development of the seeded areas.
Thank you for your continual patience and understanding throughout the process of improving your streets and utilities!
Sign Up for Project Updates
Project Contact
Spencer Johnson
Bolton & Menk, Inc.
320-979-6136
Spencer.Johnson@bolton-menk.com
City Engineer
Jared Voge
Bolton & Menk, Inc.
612-756-0326
Jared.Voge@bolton-menk.com