Parking Lot Improvements

Proposed Improvements

  • Fire Department Parking Lots Reconstruction
  • 7th Street Parking Lot Reconstruction
  • Sperryville Parking Lot

Project Updates – September 20, 2022

Work to be completed the week of September 19

  • Tolerancing of gravel base at Sperry Park in preparation for paving
  • Grading at Firehall parking lot in preparation for gravel
  • Gravel base construction and grading at Firehall parking lots
  • Grading at 7th Street SW parking lot in preparation for gravel

Work to be completed the week of September 26

  • Gravel base construction and grading at 7th Street SW parking lot
  • Concrete sidewalk, driveways, and curb & gutter construction at 7th Street SW parking lot

Contractor

Duininck, Inc.