Project Updates
August 11, 2023
- Since the last update, Henning Construction has completed the street pavement removals, street subgrade excavation, and installation of the new storm sewer system.
- Henning is currently prepping the road subgrade, installing the street edge drains, and placing the aggregate base in preparation for concrete street construction.
- The concrete pavement subcontractor is scheduled to be on site next week, August 14th, to begin constructing the concrete curbs, roadway pavement and sidewalks.
- We appreciate everyone’s patience during the progress of this project. Please contact Bolton & Menk staff (Justin Olson) at 507-848-6927 or the City Engineering office with any questions or concerns.
Anticipated Start Date
July 5, 2023
Contractor
Henning Construction
Contact Information
Travis Winter, Principal Engineer
Bolton & Menk, Inc.
612-247-5663
Travis.Winter@bolton-menk.com
Justin Olson, Project Engineer
Bolton & Menk, Inc.
507-848-6927
Justin.Olson@bolton-menk.com