Project Overview

Project Objectives

The objective of this project is to conduct necessary street and utility improvements in the area south and west of Lake Fremont

Proposed Improvements

  • Removal of the existing pavement.
  • Removal of boulevard trees which interfere with the construction.
  • Replacement of watermain, water services and curb stop.
  • Construction of storm sewer to improve drainage.
  • Rehabilitation of portions of the sanitary sewer main and manholes.
  • Replacement of a sanitary sewer forcemain.
  • Grading and construction of a new aggregate base roadbed.
  • Construction of surmountable style concrete curb and gutter.
  • Construction of a bituminous paved street.
  • Replacement of driveways up to the right-of-way.
  • Replacement of mailbox posts.
  • Restoration and seeding of the boulevards.

Contractor


Larson Excavating

Click below to sign up for project updates!


Sign up for project updates

To sign up for project updates, please enter your contact information below.

Contact Us!


Kevin Bittner

Principal Engineer

Bolton & Menk