Top
 

2024 Pavement Management Project

Project Overview

The City of Cottage Grove as part of its Pavement Management Program will be reconstructing streets in the Prestige Estates Neighborhood. At this time, pavement, curb and gutter has reached the end of its lifecycle and is due for more major maintenance. Due to the nature of the construction, the project will be constructed in multiple phases to maximize access to residents throughout construction.

Street construction is weather dependent; therefore, the schedule is subject to change. There will be ongoing communication providing project schedule updates.

Safety is the highest priority of everyone involved in this project. While the contractor will do their best to provide warning signs, barricades, and observation within the project areas, we do ask that you remind children to stay clear of the construction site and equipment

Project Updates

Phase 1 – Jenner Ave and 79th Street S

Work completed week of July 22:

  • New street lights installed

Anticipated work for week of July 29:

  • Damaged curb to be removed and replaced throughout project 8/5-8/9

Phase 2 – Jocelyn Ave

Work completed week of July 22:

  • New street lights installed

Anticipated work for week of July 29:

  • Topsoil to be placed 7/25
  • Mailboxes to be reinstalled 7/30
  • Damaged curb to be removed and replaced throughout project 8/5-8/9

*All work dates are weather dependent*

Type of Construction

Full Pavement and Curb Replacement

The project involves the removal and replacement of the existing asphalt surface as well as concrete curb and gutter. Additionally, some minor repairs to the sanitary sewer, watermain, storm sewer, and street light systems will be performed.

Location Map

Contact Us!

Have any questions about construction? Call the project hotline to leave a voicemail and a member of the project team will get back to you as soon as possible. We are also reachable by email. See contact info below.

Hotline Phone Number:

(651) 395-7696

Hotline Email Address:

Project Representative

Tim Adler

Sign Up for Updates!

To sign up for project updates, please enter your contact information below.