Atwater North Side Improvement Project Overview
The City of Atwater is reconstructing parts of the North Side of Atwater.
The improvements include:
- Asphalt streets with concrete curb and gutter
- Concrete driveway aprons
- Sanitary sewer, manholes and sewer services
- Watermain, hydrants with isolation valves, mainline valves and water services
- Storm sewer, storm manholes and catch basins
2025 Construction
The construction for the North Side Improvement Project has resumed. 2nd Street N, 3rd Street N, 4th Street N, and Ramsey Avenue W were substantially completed in 2024 with only the top course of asphalt pavement and punch list items remaining. Street and utility construction for the remaining project areas will be brought to substantial completion in 2025. Construction work will include the replacement of the streets, sanitary sewer, watermain, and storm sewer. The streets remaining to be improved include Idaho Avenue, Atlantic Avenue, Minnesota Avenue, Roosevelt Avenue, Orchard Avenue, Lincoln Street, 5th Street N, and 6th Street N.
It is highly recommended that residents who are concerned about how the construction will affect them watch the “What to Expect During Construction” video at the link provided on this page. Any questions about the project can be directed to the project contact.
Project Map
Project Update – April 25, 2025
Construction is continuing the North Side Improvements Project. The contractor’s anticipated schedule for the next three weeks is provided below:
4th Street North
Week of May 12:
- Installation of the final course of asphalt pavement. Residents will have limited access during paving operations.
3rd Street North, 2nd Street North, & Ramsey Avenue
Week of April 28:
- Final grading of the topsoil in the lawn areas (tentative)
- Seeding of the lawn areas (tentative)
Week of May 12:
- Installation of the final course of asphalt pavement. Residents will have limited access during paving operations.
Atlantic Avenue, Minnesota Avenue, Roosevelt Avenue, Orchard Avenue, Lincoln Street, Idaho Avenue, 5th Street North, and 6th Street North
Week of April 21:
- Reclaiming of existing bituminous pavement for all remaining streets has been completed
Lincoln Street North & Orchard Avenue East (Lincoln Street north of Orchard Avenue)
Week of April 21:
- Sanitary sewer
Week of April 28:
- Sanitary sewer continued
Week of May 5:
- Sanitary sewer continued
- Watermain
- Storm sewer
Week of May 12:
- Storm sewer continued
Lincoln Street North (Lincoln Street between Highway 12 and Atlantic Avenue)
Week of April 28:
- Sanitary sewer
- Watermain
Week of May 5:
- Watermain continued
- Storm sewer
Roosevelt Avenue East
Week of April 21:
- Street base construction
Week of April 28:
- Street base construction
Week of May 5:
- Curb and gutter construction
Minnesota Avenue (County Road 2 to 3rd Street North)
Week of May 12:
- Watermain
- Storm sewer
Detour Update
County Road 2 has been temporarily built to a gravel surface at the intersection of Roosevelt Avenue and has been opened back up to traffic. The intersection will remain a gravel surface until the pavement plant opens. The intersection is planned to be closed the week of May 12 to patch the pavement and will reopen to traffic thereafter.
County Road 2 Detour

Additional Notes:
Garbage/Recycling: Residents are asked to label their garbage and recycling bins by writing their house number on a piece of tape and attaching it to their bins. Place the bins near the street the day prior to pick-up days and the contractor will move them as needed for pick-up.
Temporary Mailboxes: Temporary mailboxes for Lincoln Street, Orchard Avenue, and Roosevelt Avenue are planned to be installed on the south side of the south block of Sunrise Lane on April 4.
Turf Establishment: After the seeding is completed, it is the residents’ responsibility to maintain the lawn. Residents must water the lawns to properly establish the turf. Please follow the newly seeded lawns management document to ensure the growth and development of the seeded areas.
New Concrete: After the new concrete curbing and driveways are poured, the concrete requires 7 days to build enough strength to be driven on. Please do not drive on the concrete within 7 days of its installation.
Street Paving: Residents will have limited access during paving operations. No on street parking will be available. Access in and out of driveways will be blocked at times depending on the current location of the paving operation.
Winter Concrete Care: Please refer to the Winter Concrete Care Guide for snow removal best practices to prevent damage to the new concrete.
CONTRACTOR
C & L Excavating, Saint Joseph, MN