Atwater North Side Improvement Project Overview
The City of Atwater is reconstructing parts of the North Side of Atwater.
The improvements include:
- Asphalt streets with concrete curb and gutter
- Concrete driveway aprons
- Sanitary sewer, manholes and sewer services
- Watermain, hydrants with isolation valves, mainline valves and water services
- Storm sewer, storm manholes and catch basins
2025 Construction
The construction for the North Side Improvement Project has resumed. 2nd Street N, 3rd Street N, 4th Street N, and Ramsey Avenue W were substantially completed in 2024 with only the top course of asphalt pavement and punch list items remaining. Street and utility construction for the remaining project areas will be brought to substantial completion in 2025. Construction work will include the replacement of the streets, sanitary sewer, watermain, and storm sewer. The streets remaining to be improved include Idaho Avenue, Atlantic Avenue, Minnesota Avenue, Roosevelt Avenue, Orchard Avenue, Lincoln Street, 5th Street N, and 6th Street N.
It is highly recommended that residents who are concerned about how the construction will affect them watch the “What to Expect During Construction” video at the link provided on this page. Any questions about the project can be directed to the project contact.
Project Map
Project Update – June 13, 2025
Construction is continuing on the North Side Improvement Project. The contractor’s anticipated schedule for the next two weeks is provided below:
4th Street North & Ramsey Avenue
- Construction is completed with only punchlist items remaining. If there are any items that you believe need to be addressed prior to the completion of the project, please contact Spencer Johnson at the contact information provided.
3rd Street North, 2nd Street North, & Ramsey Avenue
- Construction is completed with only punchlist items remaining. If there are any items that you believe need to be addressed prior to the completion of the project, please contact Spencer Johnson at the contact information provided.
Roosevelt Avenue East
- The base course of asphalt pavement has been installed.
- Additional updates will be provided after the Contractor provides their schedule for the topsoil grading and seeding.
Lincoln Street N & Orchard Avenue E (Lincoln Street north of Orchard Avenue)
- Week of June 16:
- Concrete curb and gutter installation.
- Concrete driveway installation.
Minnesota Avenue (County Road 2 to 3rd Street N)
- Week of June 16:
- Street base construction
- Week of June 23:
- Street base construction continued
Atlantic Avenue, 5th Street N, Minnesota Avenue (4th Street to 8th Street)
- The Contractor’s underground crew has mobilized out of town temporarily and is planning to return to start the underground utility construction on these streets after Independence Day in early to mid-July.
Additional Notes:
Punchlist Items: The improvements will be finalized at various stages throughout the project timeline. As each phase is completed, there may be a few remaining tasks that need attention before the project is fully closed out. These tasks are referred to as ‘punchlist items.’ If you believe there are any items that need attention before project completion, please reach out to Spencer Johnson.
Garbage/Recycling: Residents are asked to label their garbage and recycling bins by writing their house number on a piece of tape and attaching it to their bins. Place the bins near the street the day prior to pick-up days and the contractor will move them as needed for pick-up.
Temporary Mailboxes: Temporary mailboxes for Lincoln Street, Orchard Avenue, and Roosevelt Avenue are planned to be installed on the south side of the south block of Sunrise Lane on April 4.
Turf Establishment: After the seeding is completed, it is the residents’ responsibility to maintain the lawn. Residents must water the lawns to properly establish the turf. Please follow the newly seeded lawns management document to ensure the growth and development of the seeded areas.
New Concrete: After the new concrete curbing and driveways are poured, the concrete requires 7 days to build enough strength to be driven on. Please do not drive on the concrete within 7 days of its installation.
Street Paving: Residents will have limited access during paving operations. No on street parking will be available. Access in and out of driveways will be blocked at times depending on the current location of the paving operation.
Winter Concrete Care: Please refer to the Winter Concrete Care Guide for snow removal best practices to prevent damage to the new concrete.
CONTRACTOR
C & L Excavating, Saint Joseph, MN