1st Avenue Reconstruction

Project Overview

The City of Aurora is reconstructing the West 1st Avenue North roadway and utilities from CSAH 100 (Main Street) to Pine Grove Park (N 5th Street).  The project will replace the storm sewer, watermain distribution pipe and service laterals, and most of the sanitary sewer collection system and service laterals.  In March 2024, the City received a $1.5 million grant through MnDOT’s Local Road Improvement Program (LRIP) to assist with pavement replacement costs.  The City is actively pursuing other funding sources through the MPCA and MDH to assist with utility replacement costs.

Total Project Cost – $3 Million

Project Timeline

2024 – Preliminary & Final Design

2025 – Finalize Project Funding Plan

2026 – Construction, Substantial Completion by October 2026

2027 – Final Completion

This project is anticipated to be substantially complete in 2025 with the final pavement lift in 2026.

Project Updates

Check back here for project updates!

Click image to view larger.

Documents

Check back here for important project documents.

Sign Up for Project Updates

Contact Us!

For more information or questions regarding this project please contact:

Josh Stier, Principal Engineer
joshua.stier@bolton-menk.com

Lucas Heikkila, City Administrator
cityclerk@ci.aurora.mn.us