Project Timeline

August 20, 2018

City Council authorized the completion of a Feasibility Study

September 27, 2018

City Council approved soil borings and the completion of a geotechnical evaluation

October 2018

Soil borings completed on various roads within the project area

November 2018

Geotechnical evaluation completed and submitted

Winter 2018-19

Preliminary layout and cost estimate work

February 2019

Project website created

June 26, 2019

Public Open House held

August 2019

City Council approves project feasibility study

September 3, 2019

Public Hearing held

September 16, 2019

City Council orders improvements and authorizes final design

December 2019

Preliminary design layout completed

Winter 2019-20

Final design and plan set creation