Project Timeline
August 20, 2018
City Council authorized the completion of a Feasibility Study
September 27, 2018
City Council approved soil borings and the completion of a geotechnical evaluation
October 2018
Soil borings completed on various roads within the project area
November 2018
Geotechnical evaluation completed and submitted
Winter 2018-19
Preliminary layout and cost estimate work
February 2019
Project website created
June 26, 2019
Public Open House held
August 2019
City Council approves project feasibility study
September 3, 2019
Public Hearing held
September 16, 2019
City Council orders improvements and authorizes final design
December 2019
Preliminary design layout completed
Winter 2019-20
Final design and plan set creation