February 2017 | Authorization of engineering for design and construction services |
March – May 2017 | Preparation of plans and specifications |
March – June 2017 | City design / plan / specification reviews |
June 30, 2017 | Completion of final plans and specifications |
June 30, 2017 | Submission of plans and specifications to Minnesota Pollution Control Agency (MPCA) for review |
July 2017 | Advertisements for bids |
July 20, 2017 | Pre-bid meeting for contractors to be hosted by City |
August 1, 2017 | Bids to be received by City until 1:00 pm and then opened |
August 7, 2017 | Bid results to be reported to Public Works Commission |
August 14, 2017 | Bid results to be reported to City Council / award of contract |
September 2017 – September 2018 | Construction |