February 2017 Authorization of engineering for design and construction services
March – May 2017 Preparation of plans and specifications
March – June 2017 City design / plan / specification reviews
June 30, 2017 Completion of final plans and specifications
June 30, 2017 Submission of plans and specifications to Minnesota Pollution Control Agency (MPCA) for review
July 2017 Advertisements for bids
July 20, 2017 Pre-bid meeting for contractors to be hosted by City
August 1, 2017 Bids to be received by City until 1:00 pm and then opened
August 7, 2017 Bid results to be reported to Public Works Commission
August 14, 2017 Bid results to be reported to City Council / award of contract
September  2017 – September 2018 Construction