Lake Avenue construction project will include a full reconstruction of the existing street from CR 39 to Fairlakes Avenue. The existing street will be removed and replaced with a new concrete street section. New sanitary sewer, watermain, and storm sewer will be installed as part of the project. The construction will be staged to allow for local traffic to access the existing properties on the project. A detour will be set up for through traffic to use Woodland Avenue and Albion. The construction will begin in early June with a substantial completion date of November 2025.
Contractor
ICON LLC. 330 Highway Street E. Dodge Center, MN 55927 Office 507-634-7778
Site Map
Click to enlarge map
Project Contacts
Project Engineer Troy Nemmers, PE- 507-236-9832
Resident Project Representative Chris Paris – 507-432-6040
City of Fairmont Engineer Tyler Cowing – 507-238-3948
City of Fairmont Director of Public Works/Utilities Matt York – 507-238-3942