Construction Updates
Phasing Information
Click the map above for a larger version!
Reconstruction Project Area Update
Week of October 23
- Sod was placed on remaining Phases
- Final layer of asphalt was placed on all Phases
- Miscellaneous site cleanup occurred
Week of October 30
- Project team will be conducting a project walk through to identify any remaining items needing to be addressed this year
- Final site cleanup and any minor remaining items will be addressed
- Crosswalk blocks will be installed at multiple intersections, weather permitting
- New signs will be installed on all Phases
***This update will be the final update of 2023. The project team very much appreciates everyone’s patience throughout construction!