Project Schedule
| Prepare Feasibility Report | Spring 2024 |
| Neighborhood Information Meeting #1 | June 5, 2024 |
| Public Improvement Hearing | June 12, 2024 |
| Prepare Construction Plans & Approvals | Summer 2024 |
| Neighborhood Information Meeting #2 | September 11, 2024 |
| Obtain Bids & Award Contract | March – April 2026 |
| Neighborhood Information Meeting #3 | May 6, 2026 |
| Public Assessment Hearing | May 11, 2026 |
| Begin Construction | June 1, 2026 |
| Construction Completion | Early September 2026 |