2025 Street & Utility Improvements
Overview
N 4th Street, within the City of Le Sueur needs improvements to address failing pavement and underground utilities. Utility improvements will include sanitary sewer, watermain, storm sewer, street lighting, and City electric. The project also provides the opportunity to improve connections and safety for pedestrians and motorists.
The proposed project area will include the following street segments:
- N 4th Street from Bridge Street (CSAH 22) to Dakota Street (CSAH 35)
- Cathcart Street from Commerce Street (CSAH 22) to N 4th Street
Project Area
Project Schedule
June 2024 – Call for Public Improvement Hearing in July
August 2024 – Hold Neighborhood Info Meeting
August 2024 – Public Improvement Hearing
August 2024 – Order Preparation of Plans & Specs
November 2024 – Hold Second Neighborhood Info Meeting
February 2025 – Advertise for Bids
March 2025 – Award Bid
April 2025 – Hold Neighborhood Info Construction Meeting
May 2025 – Begin Construction
September 2025 – Hold Assessment Hearing & Adopt Assessment Roll
October 2025 – Construction Substantial Completion
November 2025 – Approve Certification of Assessment Roll & File with County Auditor
June 2026 – Construction Final Completion