2025 Street & Utility Improvements

Top
 

Project Updates

Project Updates

May 16, 2025 

Week of May 12th

  • All properties in Phase 1 have been connected to temporary water.
  • The contractor installed the sanitary sewer main and watermain on N 4th Street from Bridge Street to Swan Street.
  • The contractor began installing sanitary sewer and water services from the mains to the right-of-way on N 4th Street from Bridge Street to Swan Street.
  • Centerpoint Energy and Michels finished the necessary gas relocations throughout the project area.

Week of May 19th

  • The contractor plans to finish installing sanitary sewer and water services from the main line to the right-of-way on N 4th Street from Bridge Street to Swan Street.
  • After completing the services, the contractor will work on installing storm sewer from Bridge Street to Swan Street.
  • Either late in the week of May 19th, or early in the week of May 26th the contractor will begin installing underground utilities from Swan Street to Oak Street.

The reopening of Phase 1 is planned for early July. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025. Please reach out to the contacts listed below or visit the project website for additional information.