Project Updates
May 23, 2025
Week of May 19
- The contractor finished installing all sanitary sewer and water services from the main line to the right-of-way on N 4th Street from Bridge Street to Swan Street.
- The contractor began installing underground utilities from Swan Street to Oak Street.
Week of May 26
- The contractor will work on installing storm sewer from Bridge Street to Swan Street.
- The contractor will continue installing underground utilities from Swan Street to Oak Street.
- After all watermain testing is completed, the contractor will begin putting properties from Bridge Street to Swan Street back on city water.
The reopening of Phase 1 is planned for early July. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025. Please reach out to the contacts listed below or visit the project website for additional information.