2025 Street & Utility Improvements

Top
 

Project Updates

Project Updates

April 25, 2025

This is the first weekly construction update and the purpose of these updates will be to provide a recap of work completed over the past week and outline anticipated work for the upcoming week. The updates will typically be sent out on Friday of each week. All updates are weather and construction progress dependent. We thank you in advance for your patience and cooperation for the duration of this project.

The contractor, Kuechle Underground, is planning to begin work and close the first phase of the 2025 Street & Utility Improvements Project on Wednesday, April 30. They will be closing Phase 1 which includes N 4th St from Bridge St (CSAH 22) through Morningside Drive. Detours will be signed and will be utilizing Bridge St, N Main St, and Grove St.

In addition to the closure of Phase 1, tree removals are planned throughout the entire project area on Tuesday, April 29. All trees to be removed have been marked with a pink ribbon. The tree removals will be completed under traffic.

The contractor is planning to set up temporary water throughout Phase 1 starting the week of May 5.

All properties within the closure area will receive a door hanger notice providing more information about details like access, temporary mail, temporary water, and garbage pickup.

The reopening of Phase 1 is planned for early July. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025. Please reach out to the contacts listed below or visit the project website for additional information.