Project Updates
October 17, 2025
Week of October 13
- The intersection of Dakota Street and N. 4th Street reopened.
- The contractor finished installing underground utilities on N. 4th Street from Dakota Street to Market Street.
- The contractor poured sidewalks and driveways along N. 4th Street up to Market Street and along Cathcart Street.
- The contractor placed electric conduit along Cathcart Street and installed light poles along N. 4th Street. The lights will not be operational for a few more weeks as the contractor installs the control cabinet.
- The contractor worked on placing black dirt along N. 4th Street from Bridge Street to the north.
- The contractor reinstalled mailboxes along N. 4th Street from Bridge Street to Morningside Drive.
Week of October 20
- The contractor will work on grading and placing gravel along N. 4th Street from Market Street to Dakota Street.
- The contractor will pour curb and gutter along N. 4th Street from Market Street to Dakota Street.
- Immediately following the curb and gutter, the contractor will work on pouring sidewalk along N. 4th Street from Market Street to Dakota Street.
- The contractor will work on placing black dirt along N. 4th Street from Oak Street to the north (everywhere the sidewalk work has been completed). Please avoid parking along N. 4th Street next week to allow space for the topsoil placement. No parking signs will be posted.
- Following the black dirt installation the contractor will be installing a temporary seed mixture for erosion control over the winter. All permanent seeding will be completed next spring.
Cathcart Street and N. 4th Street from Market Street to Dakota Street are expected to reopen in mid-November. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025. Please reach out to the contacts listed below or visit the project website for additional information.