2025 Street & Utility Improvements

Top
 

Project Updates

Project Updates

August 8, 2025 

Week of August 4

  • The contractor completed sewer and water services that run from the main in the street to the property line on N. 4th Street from Morningside Drive to the entrance of St. Anne’s School.
  • The contractor started installing storm sewer from Morningside Drive working north towards the entrance to school.
  • The contractor finished installing lighting conduit and the new electric distribution conduit within Phase 1 (N. 4th Street from Bridge Street to Morningside Drive).
  • As part of the N. 4th Street Distribution Improvements, the contractor worked to install electrical services from the house to the underground conduit near the street from Oak Street to Grove Street on the west side of N. 4th Street.

Week of August 11

  • The contractor will finish installing storm sewer from Morningside Drive through the entrance to the school.
  • The contractor will work on installing watermain from north of the school entrance to Boright Street.
  • The contractor will work on installing sewer and water services from the main in the street to the property line from the school entrance towards Cathcart Street.
  • Early in the week, the contractor will work on installing electrical conduit in the area south of St. Anne’s from N. 4th Street to the Morningside Drive sidewalk.
  • Early in the week, the contractor will begin grading the road and placing gravel on N. 4th Street from Morningside Drive to north of the school entrance.
  • The contractor will also work on grading for the trail in the area south of St. Anne’s.
  • The contractor will work on grading for sidewalk on N. 4th Street from Bridge Street to Morningside Drive.
  • At the end of the week, the contractor is planning to pour curb and gutter along N. 4th Street from Morningside Drive through the St. Anne’s School Entrance.
  • The contractor will also plan to pour sidewalk and driveways in Phase 1.

The reopening of Phase 1 & 2 is planned for late August prior to the start of the next school year. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025. Please reach out to the contacts listed below or visit the project website for additional information.