2025 Street & Utility Improvements

Top
 

Project Updates

Project Updates

August 29, 2025 

Week of August 25

  • The contractor finished installing sewer and water services from the main in the street to the property line from the school entrance towards Cathcart Street.
  • The contractor worked on installing storm sewer from St. Anne’s Entrance to Market Street.
  • The contractor installed lighting conduit from Morningside Drive through the entrance to St. Anne’s School.

Week of September 1

  • The contractor will continue working on installing storm sewer from St. Anne’s Entrance to Market Street.
  • The contractor will work on installing electric conduit from Boright Street to Market Street.
  • Later in the week, the contractor will work on grading the roadway on N. 4th Street from St. Anne’s Entrance to Market Street. This will involve removing the existing material in the roadway and replacing it with gravel and installing draintile.
  • As a part of the electric distribution project, the contractor will be installing electrical services from the electric easement area to houses along the west side of N. 4th Street from Grove Street to Cathcart Street.
  • Cathcart Street from Commerce Street (CSAH 22) to N. 4th Street is scheduled to close on Wednesday, September 3.
  • On Wednesday, September 3, the contractor will mill the bituminous pavement on Cathcart Street
  • On Thursday, September 4, the contractor will remove curb and gutter and driveways along Cathcart Street.
  • The contractor will work on installing temporary water to the properties along Cathcart Street while the new watermain is under construction.
  • Utility work on Cathcart Street is scheduled to begin late next week. The first operation will involve some water shutdowns to isolate the project area. Individual notices will be handed out to those properties that are impacted.

N. 4th from St. Anne’s through Market is expected to reopen in late September. The total project is anticipated to consist of five (5) phases of construction and the project substantial completion date is November 2025.