140th Street & Utility Improvements

Project Updates

Project Updates

July 10, 2025

The contractor will begin removing concrete pavement for the full extents of the next phase of construction this Friday.  This will affect all homes from 24150 140th Street through 24210 140th Street.  We ask that all residences within these extents please have your vehicles out of your driveway Friday morning.  During this time residents will need to park and access their homes from the east and west ends of the active construction area.  Access from the west end will be available on the newly graveled surface up to the current phase.  Next week the contractor will be installing this run of sanitary sewer, followed by the storm sewer, street section grading, and the aggregate base placement.  We expect this work to be completed in approximately a month, with temporary driveway access restored at this time.  We will provide additional updates as progress is made and conditions change onsite.  Please reach out to Derek Behrens, Project Engineer, at 507-236-7660 with any questions or concerns.

July 10, 2025

Storm sewer construction in Phase 1 has been completed for the west portion of the 140th Street corridor from Stevens Cove to the east for 250 feet.  The sanitary sewer replacement has also been completed for the first run from Stevens Cove west on 140th Street.   The contractor is currently performing excavation and subgrade preparation for the street.  Once this is complete a geogrid material will be placed, then the aggregate base (gravel material) for the street.  Once the aggregate base is placed, this phase of the road can be used by residents for access.  This should be done early next week, July 14 -17, weather permitting.  Starting next week, July 14th, the contractor plans to begin construction on the next phase, east of the current construction.  This will include the east end of the current construction to 24250 140th Street.  They will start with the sanitary sewer replacement on the north side of the street, followed by the storm sewer improvements, and street subgrade/aggregate base.  During this time residents in the next phase will have limited access, with direct access to driveways being blocked for some duration of the work.  Expect around a month of little or no access to driveways during these construction improvements.  Parking at either end of the phase will be maintained by the contractor similar to the current conditions onsite for the first phase of work performed.

June 17, 2025

Storm sewer construction in Phase 1 is nearing completion for the west portion of the 140th Street corridor from Stevens Cove to the east for 250 feet.  The sanitary sewer has been determined to be in a state of disrepair that cannot be left in place and is now planned to be replaced as part of the current project.  This will change access and timeline of the construction work going forward.  Following the storm sewer, the contractor plans to start on the sanitary sewer replacement.  This will entail a bypass pumping system to keep sewer operational within the project and upstream.  The bypass will include solid piping run over ground from Stevens Cove down to the sanitary manhole at 24150 140th St for the current phase.  During this time the entire street width will be closed through the noted extents and direct access to driveways will be limited.  Residents will need to park at the end of pavement removals along the edge of the street at each end during this duration of work.  Access for Stevens Cove will be maintained west of the current construction zone.  Following completion of the sanitary sewer, the street subgrade will be prepared and aggregate base placed for the street to be installed on.  Once the base material is placed, driveways will be ramped in with gravel and driveway access will be provided before the contractor moves on to the next phase.  Rather than moving to Phase 1B at 240th Ave as previously planned, the contractor will continue working east into Phase 3 following Phase 1A.  This will allow them to continue utilizing the dewatering system while it is rented and onsite.

May 23, 2025

Starting Tuesday, May 27, the contractor will be fully closing Phase 1A from Stevens Cove to 300 feet east, past the storm outlet near 24132 140th St. while they finish installing storm sewer and begin street base preparations. At this time, we ask residents to access from 240th Ave if located west of the construction closure, and east from 140th St. up to said closure. The contractor requests that residents primarily park on the north side of the street in this area, as their equipment will be located on the south side. This closure will remain in effect until the contractor completes grading and base for the street, at which time driveways will be temped back in with gravel and access restored. We will provide an update as soon as additional information is provided by the contractor. Please reach out to our construction representative, Justus Lindsay, if you have any questions or concerns.

May 21, 2025

With Memorial Day weekend fast approaching, the contractor is requesting that all homeowners along the current dewatering extents with storage access needs for boats, trailers, etc. coordinate with them by Friday evening (May 23) to get them out. This includes all properties on the south side of 140th St from house number 24085 to 24245.

Dewatering has drawn down the groundwater level, and storm sewer through Phase 1A is currently being installed. Following the storm sewer, the street subgrade will be prepared and aggregate base placed for the street to be installed on. During this time the entire street width will be closed through the current removal extents and direct access to driveways will be limited. Residents will need to park at the end of pavement removals along the edge of the street at each end during this short duration. Once the base material is placed, driveways will be ramped in with gravel and driveway access will be provided before the contractor moves on to the next phase.

Rather than moving to Phase 1B at 240th Ave as previously planned, the contractor will continue working east into Phase 3 following Phase 1A. This will allow them to continue utilizing the dewatering system while it is rented and onsite.

May 7, 2025

Beginning Thursday, May 8, the contractor will start street pavement removals on Phase 1A, from Stevens Cove to the newly installed storm sewer outlet. During this time, we ask residents west of Stevens Cove (toward 240th Ave) to access the area from the west via 240th Ave, and residents east of Stevens Cove to continue accessing from the east via the Hill Ave intersection. Residents along the active construction zone will experience limited access during the day, with overnight access planned in the north boulevard. If you have any questions or concerns about access, please contact our Construction Project Representative.

April 29, 2025

Dewatering installation in Phase 1A will be delayed until Wednesday, April 30, due to the recent weather. The contractor will start this work Wednesday morning and is requesting that residents on the south side of 140th St in Phase 1A please have their vehicles out of their garage/driveway at this time as driveway access will become restricted for approximately 2-3 weeks. The contractor will accommodate parking on the south side of the street during this time.

April 25, 2025

Construction has officially begun on the west section of the 140th Street corridor, from 240th Avenue to Hill Avenue. Initial work includes the installation of the storm sewer outlet. However, progress has been slower than anticipated due to high groundwater levels and unstable soil conditions. To address these challenges, a dewatering process will be implemented starting next week.

Dewatering work for Phase 1A will begin Monday, April 25. This involves drilling collection holes along the south side of the road to manage groundwater levels. A collector pipe will be laid on the road surface to facilitate this process.

As a result, driveway access will be limited for residents on the south side of the road throughout Phase 1A. Residents are asked to move their vehicles out of garages and driveways by Tuesday morning to allow the installation of the dewatering system. Parking along the street will be necessary during this period. The dewatering equipment is expected to remain in place for approximately three weeks.

Once groundwater levels have been lowered, the storm sewer installation through Phase 1A will proceed. Afterward, the road subgrade will be prepared, and the aggregate base for the street will be placed. Once this base material is installed, gravel ramps will be added to restore temporary driveway access before the contractor moves forward.

Instead of proceeding to Phase 1B at 240th Avenue as originally planned, the contractor will shift work eastward into Phase 3 following the completion of Phase 1A. This adjustment allows continued use of the on-site dewatering system while it is rented and available. 

View Construction Notice 2

April 14, 2025

Construction will be commencing on the west portion of the 140th Street corridor from 240th Avenue to Hill Avenue in the coming weeks. These improvements will include replacement of the storm sewer, street subgrade, pavement, and sidewalks. During this time, access will be limited and constantly changing, but everyone will work together to maintain residential access to homes outside of working hours.

View Construction Notice 1

Contractor

Beck Excavating, Inc.

2903 15th St – P.O. Box 348
Spirit Lake, IA 51360

Phone: 712-336-0777