Construction Update – November 7, 2022

  • Hoffman Concrete plans to be done with concrete work by mid-week.
  • Duininck will be on-site at the end of the week to start black dirt work and finish the black-top tie-ins at each intersection.

 

Construction Newsletter #1 – August 5, 2022

2022 Street & Utility Improvements

Construction Update – November 7, 2022

  • Hulstein has completed concrete work on the project.  They will continue seeding and installing blanket this week.

 