Project Objectives
- Improve street surface conditions
- Replace sewer infrastructure
- Improve sidewalk conditions
- Reconstruct curb and gutter
Proposed Improvements
- Street reconstruction; concrete pavement with subsurface drains
- Concrete driveway aprons, curb and gutter
- Sanitary sewer manhole replacement
- Water and sewer lines to property lines
- Concrete sidewalk replacement to meet ADA standards
Tentative Start Date
July 17th, 2023
Contractor
Hulstein Excavating
Contact Information
Justin Zechmeister, Project Representative
Bolton & Menk, Inc.
612-258-1460
Justin.Zechmeister@bolton-menk.com
Travis Winter, Principal Engineer
Bolton & Menk, Inc.
612-247-5663