Project Updates
December 5, 2025
Summary of This Week’s Activities (November 30 – December 6)
- Continued verification and staking of existing underground utilities.
- Marked tree removals and construction limits in select areas.
Upcoming Tentative Schedule (December 7 – December 13)
- Traffic control will be installed along 202nd Street.
- Excavation for the bore pit will begin north of 202nd Street.
Previous Updates
November 21, 2025
Summary of This Week’s Activities (Week of November 21)
- Drone flight was completed for preconstruction documentation.
Upcoming Tentative Schedule (Week of November 28)
- Continued verification of existing underground utilities.
- Please note that no work will be performed in observance of Thanksgiving on Thursday, November 27.
November 14 – A drone flight is tentatively scheduled for next week over the South Center Core project area to capture preconstruction documentation. Crews are also marking utilities in preparation for upcoming construction. We ask that you please do not move stakes or flags.
November 5 – Crews will be performing underground utility locating and survey work in several areas this week to prepare for upcoming construction. Our surveyor will be on site Friday, 11/7, to place stakes at key project locations, including Sportsman Drive, 202nd Street Crossing, Emerald Pines Drive, the golf course area, and Emerald Meadows. Please do not move or remove any stakes or utility flags.
November 3 – In the coming weeks, an individual on the project team will be conducting preconstruction photo and video documentation within the project area. They will be clearly identifiable by a Bolton & Menk safety vest.
October 10, 2025 – Design is 100% completed.
September 24, 2025 – Notified qualified contractors.
September 9, 2025 – Design is 90% completed.
August 25, 2025 – Request for statement of qualifications of subcontractors has been sent.
June 12, 2025 – Community meetings to took place.
April 10, 2025 – Final design phase has begun.
October 15, 2024 – Easements have been determined; reaching out to affected property owners with documents.
September 13, 2024 – Easement procurement process is ongoing.
August 8, 2024 – Easement procurement process has begun.
May 9, 2024 – Easement needs are being determined.
Sign Up for Project Updates
Project Contacts
Josh Pope
District Engineer
Bolton & Menk, Inc.
Joshua.Pope@bolton-menk.com
(712) 363-8638
Jessica Fisher
Assistant District Engineer
Bolton & Menk, Inc.
Jessica.Fisher@bolton-menk.com
(515) 425-4311