Project Schedule
July 22, 2023: Main Street construction start
October 31, 2023: Main Street substantial completion
Spring 2024: Main Street final lift of asphalt
Spring 2024: Bridge Street construction start
Summer 2024: Pembroke Street construction start
Spring 2025: Bridge and Pembroke final lift of asphalt