Project Schedule

 

July 22, 2023: Main Street construction start

October 31,  2023: Main Street substantial completion

Spring 2024: Main Street final lift of asphalt

Spring 2024: Bridge Street construction start

Summer 2024: Pembroke Street construction start

Spring 2025: Bridge and Pembroke final lift of asphalt