Estimated Schedule of Construction Phases
Estimated Schedule of Construction Phases – Updated 6-9-2025
Please note that this schedule and the progression of phases is approximate. These time frames will vary due to a multitude of factors, which may include reasons such as weather, material deliveries, soil conditions, and number of crews. This schedule will be updated as more information becomes available.
- Concrete Preparation – Ongoing
- Concrete Work – Start the week of June 9th
– Duration: 3-4 weeks - Gravel Work Adjacent to Concrete – Start week of June 16th
– Ongoing as concrete cures - Start Asphalt Preparation and Paving
– Contractor may use gravel excavated from the street areas to level and fix alleys at this time. Start the week of July 7th.
– Expect road closures in street areas. - Final Lawn Turf Establishment
– Add and level topsoil
– Condition soil
– Place seed & fertilizer
– Spray hydromulch Mid July-Mid August 31st
– Optimum seeding window is in August
Schedule may adjust depending on weather conditions throughout the summer.