City of Wabasso - Sanitary Sewer System Improvements

Top
 

Schedule

Estimated Schedule of Construction Phases

Estimated Schedule of Construction Phases – Updated 6-9-2025

Please note that this schedule and the progression of phases is approximate. These time frames will vary due to a multitude of factors, which may include reasons such as weather, material deliveries, soil conditions, and number of crews. This schedule will be updated as more information becomes available.

  • Concrete Preparation – Ongoing
  • Concrete Work – Start the week of June 9th
    – Duration: 3-4 weeks
  • Gravel Work Adjacent to Concrete – Start week of June 16th
    – Ongoing as concrete cures
  • Start Asphalt Preparation and Paving
    – Contractor may use gravel excavated from the street areas to level and fix alleys at this time. Start the week of July 7th.
    – Expect road closures in street areas.
  • Final Lawn Turf Establishment
    – Add and level topsoil
    – Condition soil
    – Place seed & fertilizer
    – Spray hydromulch Mid July-Mid August 31st
    – Optimum seeding window is in August

Schedule may adjust depending on weather conditions throughout the summer.