City of Wabasso - Sanitary Sewer System Improvements

Top
 

Updates

Construction Updates

PROJECT UPDATE:  5-13-2024

As a part of this project, residents who live adjacent to the project areas will get their sewer service televised from their house to the sewer main free of charge. However, the Contractor will need access to your home or business in order to televise your sewer pipe and will be in contact to schedule a time that works with you. Please be on the lookout for a flier or phone call from Holtmeier Construction or their subcontractor, Underground Technologies, asking to set up a time to televise your sewer service. Please coordinate directly with the Contractor.

By coordinating with the televising, you will get your sewer service televised from the house to the sewer main free of charge and will be able to learn the condition and material of your service pipe. The city will receive the reports and footage of all the services that were televised and will be able to provide you with those reports or footage.
Thank you for your patience and cooperation!

Matt Miller, PE
Resident Project Representative
Bolton & Menk

PROJECT UPDATE:  5-8-2024

Since the last update, we have experienced a fair amount of rain that has slowed some of the construction. Holtmeier Construction has been continuing work by the lift station when conditions allow. They installed sewer pipe at the lift station site along with getting started with some sewer pipe installation on Alley G, however they stopped short of the gravel alley for the time being. Once the current work at the lift station is finished and bypass systems are set in place, they will continue construction along Alley F and Alley G, likely in the next week or so.

M.R. Paving and Excavating has been able to continue construction along Main Street due to the paved surfaces and adequate drainage. M.R. is expecting to finish construction on Main Street this week. Next week, expect construction to begin on the CIPP portion of Elm Street and Dewey Street. Work in this area will take approximately a week to complete.

Matt Miller, PE
Resident Project Representative
Bolton & Menk

PROJECT UPDATE:  4-24-2024

Over the last week, Holtmeier Construction finished the majority of their work on the northmost block of Alley F in the private easement area. Currently they are working on the preliminary plumbing for the new lift station and the forcemain. Last Wednesday, April 17th, M.R. Paving and Excavating began saw cutting pavement and concrete ahead of the sewer service replacement on Barr Street and Main Street, among the other CIPP areas. On Thursday, April 18th, the crew began service reconstruction on Barr Street and now they have continued the service reconstruction into Main Street this week.

During the work on Main Street during the day, the street will be closed to through traffic. For residents, there will still be access via TH 68 west of town or to the east. The construction will generally progress east to west on Main Street.

In the next week or so, Holtmeier Construction will return to installing pipe on Alley F and may also look at starting Alley G around that time as well. Construction in the May Street easement west of the school is tentatively scheduled for early to mid May. Work on Dewey Street is tentatively expected to start mid May as well.

M.R. Paving and Excavating will continue to reconstruct sewer services on Main Street. Expect construction to continue on Main Street for the next week or two. Following that, M.R. will move to the 1 block sections on Elm Street and Dewey Street to continue the service reconstruction ahead of the CIPP lining later this year.

Matt Miller, PE
Resident Project Representative
Bolton & Menk

PROJECT UPDATE: 4-15-2024

Last week, traffic barricades and cones were dropped of for areas of construction on the north half of Wabasso. Please do not be alarmed, we will not be closing all the streets at once! As construction progresses through town, we will use the barricades to close off a street or intersection as we work through it. As we complete construction, we will restore the road to a gravel patch and reopen the street or intersection.

Since the last update, Holtmeier Construction completed the installation of the new lift station and valve vault structures along with approximately 850’ of new 15” sanitary sewer. Looking ahead, they will continue construction along Alley F for another 200’. They will also begin construction on Alley G. However, in both instances, they will be stopping short of the existing sewer main. Before they connect to the existing sewer main, they need to install the pumps and control systems for the new lift station system and also make the connection to the wastewater treatment plant. This process will begin this week and likely carry into next week.

Also beginning this week, will be the sanitary sewer service replacement on Main Street (west of Front Street), Barr Street, Dewey Street (Elm Street to Front Street), and Elm Street (north of Dewey Street). This work will consist of reconstructing resident’s sewer services from the property line to the sewer main in the middle of the street. We will be holding a neighborhood meeting tonight at 5:30 at the intersection of Main Street and Barr Street with these residents to provide more details.

Towards the end of the month, construction will progress down the remaining two blocks of Alley F. From there, construction will begin on Dewey Street and work its way west to Elm Street. Work on Dewey Street is tentatively expected to begin early May. Any work on alleys adjacent to Dewey Street cannot begin until after construction is completed on Dewey Street east of that alley.

Thank you for your cooperation and patience!

PROJECT UPDATE:  4-3-2024

M.R. Paving & Excavating and their subcontractor, Holtmeier Construction, began the sewer work on Monday, April 1st. The first part of the project consists of constructing the structures for the new lift station. This new lift station will replace the old one at the wastewater treatment plant. Once the structures are complete, the new pumps, valves, and other components of the lift station can be installed. During the installation of these components, Holtmeier Construction will continue to construct the new 15” sanitary sewer on the north end of town before slowly working their way to Dewey Street.

In general, the construction will start on the north end of town and gradually work its way south. Dewey Street and Pine Street will be the two streets that experience heavier sewer construction, but otherwise, most of the work will take place in the alleys throughout much of Wabasso.
All sanitary sewer construction is scheduled to be complete on or before October 31st, 2024. All concrete and asphalt pavement restoration is scheduled to be complete between June 1st, 2025 & August 31st, 2025. Access to driveways and other facilities from these alleys will not be possible during the sewer construction. However, following the sewer construction, M.R. Paving & Excavating will be restoring all drivable surfaces to gravel until 2025.

Thank you for your cooperation and patience!

Matt Miller, PE
Resident Project Representative
Bolton & Menk

PROJECT UPDATE:  3-11-2024

On February 27th, the City of Wabasso held the Pre-construction Meeting for the Sanitary Sewer System Improvements project.

The first part of the project involves locating the existing sewer services via televising. This work began the week of March 4th, and will be continuing this week. For services that have obstructions or are unable to be located starting from within the street, the contractor will have to televise sewer services starting from inside the house.

The contractor will contact property owners where this is the case. Please be on the lookout for communication regarding scheduling a time to televise your sewer. Note that this is at no-cost to you.

Thank you for your cooperation!

Matt Miller, PE
Resident Project Representative
Bolton & Menk