Estimated Schedule of Construction Phases
Estimated Schedule of Construction Phases – Updated 7-29-2024
Please note that this schedule and the progression of phases is approximate. These time frames will vary due to a multitude of factors, which may include reasons such as weather, material deliveries, soil conditions, and number of crews. This schedule will be updated as more information becomes available.
Phase 1
- Sewer construction is complete.
- Surface restoration is in progress.
Phase 2
- Part A: Sewer construction and gravel restoration is complete. Turf restoration to follow.
- Part B: Sewer main trenchless lining, CIPP. Schedule for August-September.
Phase 3
- Part A: Sewer construction is complete, and restoration will follow.
- Part B: Sewer construction is in progress.
Phase 4
- Part A: Sewer construction is in progress.
- Part B: Expected to start in August.
Phase 5: Expected to start in August-September – May begin after Phase 6.
Phase 6: Expected to start in August. – May begin before Phase 5.
Phase 7: Expected to start in October.